Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Environment-friendly seabed DCM pile head removing construction technology
The invention belongs to the field of seabed DCM pile head body removing construction processes, and particularly relates to an environment-friendly seabed DCM pile head removing construction process which comprises the following steps that firstly, various construction devices of an overwater breaking excavation platform are overhauled; secondly, the overwater breaking excavation platform is moved to the position above the area to be broken and excavated, and the overwater breaking excavation platform is fixed through a winch anchor cable; 3, selecting a DCM test area to carry out a typical breaking excavation construction test; fourthly, the grab bucket is lowered to the DCM pile head body for breaking excavation; fifthly, the overwater breaking excavation platform is driven out of the first excavation area, multi-beam water depth measurement is conducted on the second excavation area, and a three-dimensional landform graph of the second excavation area is established; sixthly, analyzing the three-dimensional landform graph after breaking excavation, and continuing to construct the undercut area which does not reach the designed elevation according to the fourth to fifth steps; and 7, breaking excavation preparation work of the next area is carried out, and the steps are repeated.
本发明属于海底DCM桩头主体清除施工工艺领域,具体的说是一种环保型海底DCM桩头清除施工工艺,该施工工艺包括以下步骤:第一步:检修水上破除开挖平台的各类施工设备;第二步:将水上破除开挖平台行驶移至待破除开挖区域上方,通过绞锚缆固定水上破除开挖平台;第三步:选取DCM试验区域进行破除开挖典型施工试验;第四步:将抓斗下放至DCM桩头主体处进行破除开挖;第五步:将水上破除开挖平台驶出第一开挖区域,对第二开挖区域进行多波束水深测量,建立第二开挖区域的三维地貌图形;第六步:分析破除开挖后的三维地貌图形,对没有达到设计标高的欠挖区域按照第四至第五步继续施工;第七步:进行下一区域的破除开挖准备工作,以此循环。
Environment-friendly seabed DCM pile head removing construction technology
The invention belongs to the field of seabed DCM pile head body removing construction processes, and particularly relates to an environment-friendly seabed DCM pile head removing construction process which comprises the following steps that firstly, various construction devices of an overwater breaking excavation platform are overhauled; secondly, the overwater breaking excavation platform is moved to the position above the area to be broken and excavated, and the overwater breaking excavation platform is fixed through a winch anchor cable; 3, selecting a DCM test area to carry out a typical breaking excavation construction test; fourthly, the grab bucket is lowered to the DCM pile head body for breaking excavation; fifthly, the overwater breaking excavation platform is driven out of the first excavation area, multi-beam water depth measurement is conducted on the second excavation area, and a three-dimensional landform graph of the second excavation area is established; sixthly, analyzing the three-dimensional landform graph after breaking excavation, and continuing to construct the undercut area which does not reach the designed elevation according to the fourth to fifth steps; and 7, breaking excavation preparation work of the next area is carried out, and the steps are repeated.
本发明属于海底DCM桩头主体清除施工工艺领域,具体的说是一种环保型海底DCM桩头清除施工工艺,该施工工艺包括以下步骤:第一步:检修水上破除开挖平台的各类施工设备;第二步:将水上破除开挖平台行驶移至待破除开挖区域上方,通过绞锚缆固定水上破除开挖平台;第三步:选取DCM试验区域进行破除开挖典型施工试验;第四步:将抓斗下放至DCM桩头主体处进行破除开挖;第五步:将水上破除开挖平台驶出第一开挖区域,对第二开挖区域进行多波束水深测量,建立第二开挖区域的三维地貌图形;第六步:分析破除开挖后的三维地貌图形,对没有达到设计标高的欠挖区域按照第四至第五步继续施工;第七步:进行下一区域的破除开挖准备工作,以此循环。
Environment-friendly seabed DCM pile head removing construction technology
一种环保型海底DCM桩头清除施工工艺
MA DINGQIANG (Autor:in) / LI ZHONGHAO (Autor:in) / LIAO ZENGPING (Autor:in) / ZHONG XUHUA (Autor:in) / YANG ZHENHUA (Autor:in) / ZHANG PENG (Autor:in) / YU MINGJIE (Autor:in) / ZHANG YINGKAI (Autor:in) / HU QIAN (Autor:in) / LUO ZIQIANG (Autor:in)
14.10.2022
Patent
Elektronische Ressource
Chinesisch
Pre-fractured drilling pile head removing construction method
Europäisches Patentamt | 2020
|Environment-friendly and efficient pile head eradicating method
Europäisches Patentamt | 2020
|Construction system and method of seabed concrete pile
Europäisches Patentamt | 2024
|PILE DEVICE FOR SEABED FOUNDATION AND SEABED FOUNDATION CONSTRUCTION METHOD USING THE SAME
Europäisches Patentamt | 2024
|ENVIRONMENTALLY FRIENDLY SUBMARINE DCM PILE HEAD CLEARING CONSTRUCTION PROCESS
Europäisches Patentamt | 2023
|