Shaped deep foundation pit dewatering well operation platform and construction method thereof
The invention discloses a shaped deep foundation pit dewatering well operation platform which comprises a supporting framework, a U-shaped bolt, a protective barrier, a safety net, a walkway plate and a supporting structure. The U-shaped bolt is pre-buried in the supporting structure, and the lower portion of one end of the supporting framework is connected with the U-shaped bolt through a nut; the lower portion of the other end of the supporting framework is connected with a steel sleeve of the dewatering well through a first inclined supporting rod, the protective handrail is installed on the side edge of the supporting framework, the walkway plate is laid on the supporting framework, the safety net is installed on the protective handrail, the outer side edge of the protective handrail is connected with a second inclined supporting rod, and the second inclined supporting rod is fixed to the foundation column through an expansion bolt. Compared with the prior art, the operation platform has the beneficial effects that the operation platform is customized and machined in advance, and is welded and assembled on a foundation pit construction site, so that standardization, shaping and factorization of the deep foundation pit dewatering well operation platform are realized; and the safety when the operation platform is used for water level observation and water pump maintenance work is ensured.
本发明公开了一种定型化深基坑降水井操作平台,包括支撑骨架、U型螺栓、防护栏杆、安全网、走道板和支撑结构,U型螺栓预埋在支撑结构内,支撑骨架的一端下部通过螺母与U型螺栓连接,支撑骨架的另一端下部通过第一斜撑杆与降水井的钢套连接,防护栏杆安装在支撑骨架的侧边位置,走道板铺装在支撑骨架上,安全网装在防护栏杆上,防护栏杆的外侧边连接有第二斜撑杆,第二斜撑杆通过膨胀螺栓固定在基础柱上。与现有技术相比,本发明有益效果:本发明通过在对操作平台提前进行定制加工,在基坑工地进行焊接组装,实现深基坑降水井操作平台标准化、定型化、工厂化,有防护栏杆、安全网结构,保证了利用操作平台进行水位观测和水泵修检工作时的安全。
Shaped deep foundation pit dewatering well operation platform and construction method thereof
The invention discloses a shaped deep foundation pit dewatering well operation platform which comprises a supporting framework, a U-shaped bolt, a protective barrier, a safety net, a walkway plate and a supporting structure. The U-shaped bolt is pre-buried in the supporting structure, and the lower portion of one end of the supporting framework is connected with the U-shaped bolt through a nut; the lower portion of the other end of the supporting framework is connected with a steel sleeve of the dewatering well through a first inclined supporting rod, the protective handrail is installed on the side edge of the supporting framework, the walkway plate is laid on the supporting framework, the safety net is installed on the protective handrail, the outer side edge of the protective handrail is connected with a second inclined supporting rod, and the second inclined supporting rod is fixed to the foundation column through an expansion bolt. Compared with the prior art, the operation platform has the beneficial effects that the operation platform is customized and machined in advance, and is welded and assembled on a foundation pit construction site, so that standardization, shaping and factorization of the deep foundation pit dewatering well operation platform are realized; and the safety when the operation platform is used for water level observation and water pump maintenance work is ensured.
本发明公开了一种定型化深基坑降水井操作平台,包括支撑骨架、U型螺栓、防护栏杆、安全网、走道板和支撑结构,U型螺栓预埋在支撑结构内,支撑骨架的一端下部通过螺母与U型螺栓连接,支撑骨架的另一端下部通过第一斜撑杆与降水井的钢套连接,防护栏杆安装在支撑骨架的侧边位置,走道板铺装在支撑骨架上,安全网装在防护栏杆上,防护栏杆的外侧边连接有第二斜撑杆,第二斜撑杆通过膨胀螺栓固定在基础柱上。与现有技术相比,本发明有益效果:本发明通过在对操作平台提前进行定制加工,在基坑工地进行焊接组装,实现深基坑降水井操作平台标准化、定型化、工厂化,有防护栏杆、安全网结构,保证了利用操作平台进行水位观测和水泵修检工作时的安全。
Shaped deep foundation pit dewatering well operation platform and construction method thereof
一种定型化深基坑降水井操作平台及其施工方法
WANG WEI (Autor:in) / LI MAO (Autor:in) / NI SENBANG (Autor:in) / ZHAO DONGDONG (Autor:in) / GUO TIANXIN (Autor:in) / YANG YOUKE (Autor:in) / DAI XIANGJUN (Autor:in) / WU LIN (Autor:in) / JIAN XIANGWEI (Autor:in)
23.06.2023
Patent
Elektronische Ressource
Chinesisch
Dewatering well-free dewatering construction method for deep foundation pit
Europäisches Patentamt | 2022
|Open cut deep foundation pit dewatering operation platform
Europäisches Patentamt | 2023
|Foundation pit dewatering well and construction method thereof
Europäisches Patentamt | 2024
|Deep soft foundation pit dewatering well and construction method
Europäisches Patentamt | 2024
|Subway deep foundation pit well point dewatering system and construction method thereof
Europäisches Patentamt | 2020
|