Foundation construction method of construction hoist
The invention discloses a foundation construction method for a construction hoist, which comprises the following steps: in an early construction stage, planning the installation position of the construction hoist and determining the vertical axis of the installation of the construction hoist so as to position the specific position of a support column; before a building main body is constructed, concrete is poured into the side slope of the pit of the underground layer of the building main body; when a building main body is constructed, firstly, a building body and a foundation pit for positioning the supporting column are formed in the bottom of the pit of the underground layer, finally, the designed supporting column steel reinforcement framework is vertically installed on the supporting cushion layer, and after mold sealing is conducted on the supporting column steel reinforcement framework, concrete pouring construction is conducted on the supporting column steel reinforcement framework and the building main body together. And after the poured concrete reaches the strength to form the positioning supporting columns, a top plate foundation of the underground layer is constructed at the opening of the pit of the underground layer, and after the top plate foundation reaches the strength, earthwork is used for backfilling the peripheries of the positioning supporting columns. The situation that the installation foundation is impacted to collapse due to the fact that the load of the construction hoist is too large can be prevented, and the overall stability and installability of the hoist are guaranteed.
本发明公开了一种施工升降机基础施工方法,在前期施工阶段,规划好施工升降机安装位置并确定施工升降机安装的竖直轴线,以便定位支撑柱具体位置;在建筑主体施工前,先对建筑主体的地下层凹坑的边坡浇注混凝土;在建筑主体施工时,先在地下层凹坑的底部开设建筑体和定位支撑柱的基坑,最后将设计好的支撑柱钢筋骨架竖立安装于支撑垫层上,对支撑柱钢筋骨架进行封模后与建筑主体一起浇筑混凝土施工;待所浇注的混凝土达到强度形成定位支撑柱后,在地下层凹坑口部施工地下层的顶板基础,待顶板基础达到强度后,使用土方在定位支柱外围进行回填。本发明能防止施工升降机载荷过大而冲击安装基础出现坍塌的情况,保证升降机整体的稳定性和安装性。
Foundation construction method of construction hoist
The invention discloses a foundation construction method for a construction hoist, which comprises the following steps: in an early construction stage, planning the installation position of the construction hoist and determining the vertical axis of the installation of the construction hoist so as to position the specific position of a support column; before a building main body is constructed, concrete is poured into the side slope of the pit of the underground layer of the building main body; when a building main body is constructed, firstly, a building body and a foundation pit for positioning the supporting column are formed in the bottom of the pit of the underground layer, finally, the designed supporting column steel reinforcement framework is vertically installed on the supporting cushion layer, and after mold sealing is conducted on the supporting column steel reinforcement framework, concrete pouring construction is conducted on the supporting column steel reinforcement framework and the building main body together. And after the poured concrete reaches the strength to form the positioning supporting columns, a top plate foundation of the underground layer is constructed at the opening of the pit of the underground layer, and after the top plate foundation reaches the strength, earthwork is used for backfilling the peripheries of the positioning supporting columns. The situation that the installation foundation is impacted to collapse due to the fact that the load of the construction hoist is too large can be prevented, and the overall stability and installability of the hoist are guaranteed.
本发明公开了一种施工升降机基础施工方法,在前期施工阶段,规划好施工升降机安装位置并确定施工升降机安装的竖直轴线,以便定位支撑柱具体位置;在建筑主体施工前,先对建筑主体的地下层凹坑的边坡浇注混凝土;在建筑主体施工时,先在地下层凹坑的底部开设建筑体和定位支撑柱的基坑,最后将设计好的支撑柱钢筋骨架竖立安装于支撑垫层上,对支撑柱钢筋骨架进行封模后与建筑主体一起浇筑混凝土施工;待所浇注的混凝土达到强度形成定位支撑柱后,在地下层凹坑口部施工地下层的顶板基础,待顶板基础达到强度后,使用土方在定位支柱外围进行回填。本发明能防止施工升降机载荷过大而冲击安装基础出现坍塌的情况,保证升降机整体的稳定性和安装性。
Foundation construction method of construction hoist
一种施工升降机基础施工方法
HUANG CHUAN (Autor:in) / SU WEIHUA (Autor:in) / TAN YAOLONG (Autor:in) / SON RANG-KI (Autor:in) / WEI JINGTING (Autor:in) / LI YIJUN (Autor:in) / TANG SIHAI (Autor:in) / LEE BIN-NA (Autor:in) / MO XUANCAI (Autor:in)
30.01.2024
Patent
Elektronische Ressource
Chinesisch
Construction hoist foundation and construction method of construction hoist
Europäisches Patentamt | 2021
|Basement roof construction hoist foundation construction method
Europäisches Patentamt | 2023
|Construction hoist foundation support back-jacking construction method
Europäisches Patentamt | 2024
|