Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Entity-frame combined assembly type high-pile wharf structure and construction method
The invention provides an entity-frame combined assembly type high-pile wharf structure and a construction method, and belongs to the technical field of port wharf engineering. The structure comprises a cross beam component, a longitudinal beam, a U-shaped pipe ditch longitudinal beam and a panel, the cross beam part comprises an upper cross beam and a lower cross beam; the U-shaped pipe ditch longitudinal beam is composed of a side wall, a bottom plate, a pipe ditch longitudinal beam bracket and a reserved bottom plate. According to the construction method, the upper cross beam is locally holed according to the trend of a field pipeline, the U-shaped pipe ditch longitudinal beam and the upper cross beam are in vertical lap joint, finally, the panel is placed on the U-shaped pipe ditch longitudinal beam, and splicing is completed. By innovating the prefabricated structure shape, an entity-frame type lower-layer platform penetrating through the whole wharf is formed in a wharf structure system, the overall space utilization rate is greatly increased, various pipelines can be intensively arranged and contained in the lower-layer platform, maintenance work such as cable taking and pipeline overhauling by personnel is facilitated, the construction efficiency is further improved, and the construction cost is reduced. The method can be widely applied to comprehensive guarantee wharfs.
本发明提供一种实体‑框架组合装配式高桩码头结构及施工方法,属于港口码头工程技术领域。本发明的结构包括横梁部件、纵梁、U型管沟纵梁和面板;所述横梁部件包括上横梁和下横梁;所述U型管沟纵梁由侧壁、底板、管沟纵梁牛腿和预留底板组成。本发明的施工方法,通过现场管线走向,对上横梁局部开孔,并将U型管沟纵梁与上横梁垂直搭接,最后将面板搁置在U型管沟纵梁上,完成拼装。本发明通过创新预制结构形状,在码头结构体系中形成了贯穿整个码头的实体‑框架型下层平台,整体空间利用率大大提升,各类管线均能集中布置纳入下层平台,方便人员带缆、管线检修等维护工作,进一步提高施工效率,可广泛应用于综合保障码头。
Entity-frame combined assembly type high-pile wharf structure and construction method
The invention provides an entity-frame combined assembly type high-pile wharf structure and a construction method, and belongs to the technical field of port wharf engineering. The structure comprises a cross beam component, a longitudinal beam, a U-shaped pipe ditch longitudinal beam and a panel, the cross beam part comprises an upper cross beam and a lower cross beam; the U-shaped pipe ditch longitudinal beam is composed of a side wall, a bottom plate, a pipe ditch longitudinal beam bracket and a reserved bottom plate. According to the construction method, the upper cross beam is locally holed according to the trend of a field pipeline, the U-shaped pipe ditch longitudinal beam and the upper cross beam are in vertical lap joint, finally, the panel is placed on the U-shaped pipe ditch longitudinal beam, and splicing is completed. By innovating the prefabricated structure shape, an entity-frame type lower-layer platform penetrating through the whole wharf is formed in a wharf structure system, the overall space utilization rate is greatly increased, various pipelines can be intensively arranged and contained in the lower-layer platform, maintenance work such as cable taking and pipeline overhauling by personnel is facilitated, the construction efficiency is further improved, and the construction cost is reduced. The method can be widely applied to comprehensive guarantee wharfs.
本发明提供一种实体‑框架组合装配式高桩码头结构及施工方法,属于港口码头工程技术领域。本发明的结构包括横梁部件、纵梁、U型管沟纵梁和面板;所述横梁部件包括上横梁和下横梁;所述U型管沟纵梁由侧壁、底板、管沟纵梁牛腿和预留底板组成。本发明的施工方法,通过现场管线走向,对上横梁局部开孔,并将U型管沟纵梁与上横梁垂直搭接,最后将面板搁置在U型管沟纵梁上,完成拼装。本发明通过创新预制结构形状,在码头结构体系中形成了贯穿整个码头的实体‑框架型下层平台,整体空间利用率大大提升,各类管线均能集中布置纳入下层平台,方便人员带缆、管线检修等维护工作,进一步提高施工效率,可广泛应用于综合保障码头。
Entity-frame combined assembly type high-pile wharf structure and construction method
一种实体-框架组合装配式高桩码头结构及施工方法
HAN JIANYANG (Autor:in) / CHEN HAIFENG (Autor:in) / ZHANG LEI (Autor:in) / LI WENJUN (Autor:in) / ZHANG HAO (Autor:in) / YANG JIAN (Autor:in) / YANG LINGQUN (Autor:in)
08.03.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
/
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
/
F16L
PIPES
,
Rohre
/
H02G
INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
,
Verlegen oder Installieren elektrischer Kabel oder Leitungen, Verlegen oder Installieren kombinierter optischer und elektrischer Kabel oder Leitungen
Europäisches Patentamt | 2024
|Installation type high-pile wharf structure and construction method
Europäisches Patentamt | 2021
|Modularized assembly type high-pile wharf structure, construction method and monitoring system
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|