Fabricated cooling tower and construction process thereof
The invention discloses an assembly type cooling tower and a construction process thereof, and relates to the technical field of cooling equipment. The adjusting system comprises an adjusting assembly arranged around the lower end of the stand column; one end of the adjusting assembly abuts against the stand column, the other end of the adjusting assembly abuts against the inner wall surface of the pit, and the adjusting system is used for adjusting the sag and/or horizontal position of the stand column. And the filling material is filled and cured in the pit. The construction technology comprises the steps that a pit is manufactured in a foundation; a prefabricated and formed stand column is vertically placed in the pit; the height position, the perpendicularity and/or the horizontal position of the stand column are/is adjusted; and filling a filling material into the pit and curing. According to the stele-shaped foundation and the mortise and tenon connecting structure, the construction efficiency of the fabricated cooling tower can be greatly improved.
装配式冷却塔及其施工工艺,涉及冷却设备技术领域,该装配式冷却塔包括:预制成型的立柱,下端位于地基上的凹坑内;调整系统,包括围绕立柱的下端布设的调整组件;调整组件的一端与立柱相抵,另一端与凹坑的内壁表面相抵,调整系统用于调整立柱的垂度和/或水平位置;填充材料,填充且固化于凹坑内。该施工工艺包括在地基制作凹坑;将预制成型的立柱竖向放置于凹坑内;调整立柱的高度位置、垂直度和/或水平位置;在凹坑内灌入填充材料并固化。本申请的碑型基础和卯榫连接结构能够大幅地提高装配式冷却塔的施工效率。
Fabricated cooling tower and construction process thereof
The invention discloses an assembly type cooling tower and a construction process thereof, and relates to the technical field of cooling equipment. The adjusting system comprises an adjusting assembly arranged around the lower end of the stand column; one end of the adjusting assembly abuts against the stand column, the other end of the adjusting assembly abuts against the inner wall surface of the pit, and the adjusting system is used for adjusting the sag and/or horizontal position of the stand column. And the filling material is filled and cured in the pit. The construction technology comprises the steps that a pit is manufactured in a foundation; a prefabricated and formed stand column is vertically placed in the pit; the height position, the perpendicularity and/or the horizontal position of the stand column are/is adjusted; and filling a filling material into the pit and curing. According to the stele-shaped foundation and the mortise and tenon connecting structure, the construction efficiency of the fabricated cooling tower can be greatly improved.
装配式冷却塔及其施工工艺,涉及冷却设备技术领域,该装配式冷却塔包括:预制成型的立柱,下端位于地基上的凹坑内;调整系统,包括围绕立柱的下端布设的调整组件;调整组件的一端与立柱相抵,另一端与凹坑的内壁表面相抵,调整系统用于调整立柱的垂度和/或水平位置;填充材料,填充且固化于凹坑内。该施工工艺包括在地基制作凹坑;将预制成型的立柱竖向放置于凹坑内;调整立柱的高度位置、垂直度和/或水平位置;在凹坑内灌入填充材料并固化。本申请的碑型基础和卯榫连接结构能够大幅地提高装配式冷却塔的施工效率。
Fabricated cooling tower and construction process thereof
装配式冷却塔及其施工工艺
ZHANG RUI (Autor:in) / YU QIANG (Autor:in) / WANG ZIYU (Autor:in) / BAI TIANXIANG (Autor:in) / SONG NING (Autor:in) / LI JINPENG (Autor:in) / LIU JUNHONG (Autor:in) / LI JIN (Autor:in) / GAO JINCHENG (Autor:in) / CUI ZHIMENG (Autor:in)
22.03.2024
Patent
Elektronische Ressource
Chinesisch
Cooling tower and construction method of cooling tower
Europäisches Patentamt | 2024
|Fabricated mixed tower fan foundation and construction method thereof
Europäisches Patentamt | 2024
|Fabricated steel tower fan foundation and construction method thereof
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2024
|Modern cooling tower construction
Engineering Index Backfile | 1925
|