Full framing foundation treatment method under complex terrain conditions
The invention provides a method for treating a full framing foundation under a complex terrain condition. The method comprises the following specific steps: firstly, confirming different terrains on a complex terrain road section needing to be constructed; and then the different terrains determined and distinguished are constructed according to the corresponding full framing foundation treatment method. The complex terrains at least comprise four different terrains, namely a steep rock mass position, a special-shaped surface protecting wall or retaining wall position, a vertical wall surface position of the surface protecting wall or retaining wall and a rock mass position, a surface protecting wall position or a retaining wall position. By manufacturing, installing and pouring the overhanging structure, the supporting beam structure, the concrete pedestal or the concrete foundation which are simple, the problem of treatment of the full framing foundation under the complex terrain condition is effectively solved. The whole construction process is safe, controllable, convenient and fast, does not occupy more manpower or equipment, adopts common materials for construction, is small in use amount, can be processed through excess materials, and has good economical efficiency and applicability.
本发明提供一种复杂地形条件下满堂支架基础处治方法,具体步骤为:首先在需要施工的复杂地形路段进行不同地形的确认;然后对确认区分出来的不同的地形按照对应的满堂支架基础处治方法进行施工。所述的复杂地形至少包括四种不同的地形,四种不同的地形分别为:陡峭岩体处,异形护面墙或挡墙处,护面墙或挡墙竖直墙面处和岩体、护面墙或挡墙处。本发明通过制作、安装、浇筑简易的外挑结构、支撑梁结构、混凝土台座或混凝土基础,有效的解决了复杂地形条件下的满堂支架基础处治问题。整个施工过程安全可控、方便快捷,不占用较多人力或设备,所用材料均为施工常用材料,且用量较小,可通过余料加工,具有很好的经济性与适用性。
Full framing foundation treatment method under complex terrain conditions
The invention provides a method for treating a full framing foundation under a complex terrain condition. The method comprises the following specific steps: firstly, confirming different terrains on a complex terrain road section needing to be constructed; and then the different terrains determined and distinguished are constructed according to the corresponding full framing foundation treatment method. The complex terrains at least comprise four different terrains, namely a steep rock mass position, a special-shaped surface protecting wall or retaining wall position, a vertical wall surface position of the surface protecting wall or retaining wall and a rock mass position, a surface protecting wall position or a retaining wall position. By manufacturing, installing and pouring the overhanging structure, the supporting beam structure, the concrete pedestal or the concrete foundation which are simple, the problem of treatment of the full framing foundation under the complex terrain condition is effectively solved. The whole construction process is safe, controllable, convenient and fast, does not occupy more manpower or equipment, adopts common materials for construction, is small in use amount, can be processed through excess materials, and has good economical efficiency and applicability.
本发明提供一种复杂地形条件下满堂支架基础处治方法,具体步骤为:首先在需要施工的复杂地形路段进行不同地形的确认;然后对确认区分出来的不同的地形按照对应的满堂支架基础处治方法进行施工。所述的复杂地形至少包括四种不同的地形,四种不同的地形分别为:陡峭岩体处,异形护面墙或挡墙处,护面墙或挡墙竖直墙面处和岩体、护面墙或挡墙处。本发明通过制作、安装、浇筑简易的外挑结构、支撑梁结构、混凝土台座或混凝土基础,有效的解决了复杂地形条件下的满堂支架基础处治问题。整个施工过程安全可控、方便快捷,不占用较多人力或设备,所用材料均为施工常用材料,且用量较小,可通过余料加工,具有很好的经济性与适用性。
Full framing foundation treatment method under complex terrain conditions
复杂地形条件下满堂支架基础处治方法
JI XIAOZHUANG (Autor:in) / LI XUDONG (Autor:in) / LIU LEI (Autor:in) / XU XUANXUAN (Autor:in) / WANG KUN (Autor:in) / LI HAORAN (Autor:in) / XIAO CHUAN (Autor:in)
09.04.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Recyclable full framing foundation and construction method thereof
Europäisches Patentamt | 2023
|Construction method for cast-in-place beam construction full framing foundation treatment
Europäisches Patentamt | 2023
|Full framing foundation treatment method based on rapid excavation of bearing platform
Europäisches Patentamt | 2023
|Full framing turnover foundation structure and construction method thereof
Europäisches Patentamt | 2022
|