Cast-in-place pile construction method based on BIM model pile foundation
The invention relates to the technical field of cast-in-place piles, in particular to a cast-in-place pile construction method based on a BIM model pile foundation, and the method comprises the following steps: obtaining geometric information data and material information data of a target cast-in-place pile foundation according to BIM model data; the initial concrete pouring speed of the pile foundation of the target cast-in-place pile is determined according to the geometric information data; the initial concrete pouring speed is adjusted according to the material information and the environment temperature data, and the final concrete pouring speed is obtained; according to the geometric information data, the initial vibration frequency and the initial vibration force in the concrete vibration process of the pile foundation of the target cast-in-place pile are determined; the initial vibration force is adjusted according to the environment temperature data, and the final vibration force is obtained; and the vibrating process of the target cast-in-place pile foundation is completed according to the initial vibrating frequency and the final vibrating force. According to the method, the BIM model data and the environment temperature data are used, accurate control over the concrete pouring and vibrating process of the cast-in-place pile foundation can be achieved, and the engineering efficiency is improved.
本发明涉及灌注桩技术领域,具体涉及一种基于BIM模型桩基的灌注桩施工方法,该方法包括:根据BIM模型数据获取目标灌注桩桩基的几何信息数据和物料信息数据;根据几何信息数据确定目标灌注桩桩基的混凝土浇筑初始速度;根据物料信息和环境温度数据对初始混凝土浇筑速度进行调整获得混凝土浇筑最终速度;根据几何信息数据确定目标灌注桩桩基的混凝土振捣过程中的初始振捣频率和初始振捣力度;并根据环境温度数据对初始振捣力度进行调整,获得最终振捣力度;根据初始振捣频率和最终振捣力度完成对目标灌注桩桩基的振捣过程。本发明通过使用BIM模型数据和环境温度数据,可以实现对灌注桩桩基混凝土浇筑和振捣过程的精确控制,提高工程效率。
Cast-in-place pile construction method based on BIM model pile foundation
The invention relates to the technical field of cast-in-place piles, in particular to a cast-in-place pile construction method based on a BIM model pile foundation, and the method comprises the following steps: obtaining geometric information data and material information data of a target cast-in-place pile foundation according to BIM model data; the initial concrete pouring speed of the pile foundation of the target cast-in-place pile is determined according to the geometric information data; the initial concrete pouring speed is adjusted according to the material information and the environment temperature data, and the final concrete pouring speed is obtained; according to the geometric information data, the initial vibration frequency and the initial vibration force in the concrete vibration process of the pile foundation of the target cast-in-place pile are determined; the initial vibration force is adjusted according to the environment temperature data, and the final vibration force is obtained; and the vibrating process of the target cast-in-place pile foundation is completed according to the initial vibrating frequency and the final vibrating force. According to the method, the BIM model data and the environment temperature data are used, accurate control over the concrete pouring and vibrating process of the cast-in-place pile foundation can be achieved, and the engineering efficiency is improved.
本发明涉及灌注桩技术领域,具体涉及一种基于BIM模型桩基的灌注桩施工方法,该方法包括:根据BIM模型数据获取目标灌注桩桩基的几何信息数据和物料信息数据;根据几何信息数据确定目标灌注桩桩基的混凝土浇筑初始速度;根据物料信息和环境温度数据对初始混凝土浇筑速度进行调整获得混凝土浇筑最终速度;根据几何信息数据确定目标灌注桩桩基的混凝土振捣过程中的初始振捣频率和初始振捣力度;并根据环境温度数据对初始振捣力度进行调整,获得最终振捣力度;根据初始振捣频率和最终振捣力度完成对目标灌注桩桩基的振捣过程。本发明通过使用BIM模型数据和环境温度数据,可以实现对灌注桩桩基混凝土浇筑和振捣过程的精确控制,提高工程效率。
Cast-in-place pile construction method based on BIM model pile foundation
一种基于BIM模型桩基的灌注桩施工方法
WU JUNHUA (Autor:in) / LI YI (Autor:in) / ZHANG WEIJIE (Autor:in) / YANG ZHUORUI (Autor:in) / LIU XIAOLONG (Autor:in) / XU JINGNAN (Autor:in) / LI JIANQI (Autor:in)
16.04.2024
Patent
Elektronische Ressource
Chinesisch
Pile foundation casing and construction method of cast-in-place pile
Europäisches Patentamt | 2023
|Grouting device of cast-in-place pile foundation and construction method of cast-in-place pile
Europäisches Patentamt | 2023
|Photovoltaic cast-in-place pile foundation construction process
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2020
|CONSTRUCTION METHOD OF CAST-IN-PLACE PILE AND FOUNDATION
Europäisches Patentamt | 2018
|