Cable crane main cable force control method, system and equipment and readable storage medium
The invention discloses a cable crane main cable force control method, system and equipment and a readable storage medium, and relates to the technical field of bridge construction, and the cable crane main cable force control method comprises the steps that a main cable empty cable sag calculation value is determined according to a preset main cable empty cable sag deviation value by taking a main cable empty cable sag design value as a benchmark; based on the main cable empty cable sag calculation value, calculating a corresponding first cable force when the crown block is in a no-load state and a corresponding second cable force when the crown block is in a full-load state; determining a main cable empty cable sag deviation limit value according to the first cable force, the second cable force, a preset cable force deviation allowable value and the main cable empty cable sag deviation value; and controlling the sag deviation of the main cable according to the empty cable sag deviation limit value of the main cable in the construction stage of the main cable. According to the method, the safety risk during construction of the main cable of the cable crane is reduced, and the cable force deviation of the main cable in the use process of the cable crane is ensured to be within a specified limit range.
一种缆索吊机主索索力控制方法、系统、设备及可读存储介质,涉及桥梁建造技术领域,包括以主索空索垂度设计值为基准,根据预设的主索空索垂度偏差值确定出主索空索垂度计算值;基于所述主索空索垂度计算值计算出天车空载时对应的第一索力以及天车满载时对应的第二索力;根据所述第一索力、第二索力、预设的索力偏差允许值和所述主索空索垂度偏差值确定出主索空索垂度偏差限值;在主索施工阶段根据所述主索空索垂度偏差限值对主索垂度偏差进行控制。本申请降低了缆索吊机主索施工时的安全风险,保证了缆索吊机使用过程中主索索力偏差在规定限值范围内。
Cable crane main cable force control method, system and equipment and readable storage medium
The invention discloses a cable crane main cable force control method, system and equipment and a readable storage medium, and relates to the technical field of bridge construction, and the cable crane main cable force control method comprises the steps that a main cable empty cable sag calculation value is determined according to a preset main cable empty cable sag deviation value by taking a main cable empty cable sag design value as a benchmark; based on the main cable empty cable sag calculation value, calculating a corresponding first cable force when the crown block is in a no-load state and a corresponding second cable force when the crown block is in a full-load state; determining a main cable empty cable sag deviation limit value according to the first cable force, the second cable force, a preset cable force deviation allowable value and the main cable empty cable sag deviation value; and controlling the sag deviation of the main cable according to the empty cable sag deviation limit value of the main cable in the construction stage of the main cable. According to the method, the safety risk during construction of the main cable of the cable crane is reduced, and the cable force deviation of the main cable in the use process of the cable crane is ensured to be within a specified limit range.
一种缆索吊机主索索力控制方法、系统、设备及可读存储介质,涉及桥梁建造技术领域,包括以主索空索垂度设计值为基准,根据预设的主索空索垂度偏差值确定出主索空索垂度计算值;基于所述主索空索垂度计算值计算出天车空载时对应的第一索力以及天车满载时对应的第二索力;根据所述第一索力、第二索力、预设的索力偏差允许值和所述主索空索垂度偏差值确定出主索空索垂度偏差限值;在主索施工阶段根据所述主索空索垂度偏差限值对主索垂度偏差进行控制。本申请降低了缆索吊机主索施工时的安全风险,保证了缆索吊机使用过程中主索索力偏差在规定限值范围内。
Cable crane main cable force control method, system and equipment and readable storage medium
缆索吊机主索索力控制方法、系统、设备及可读存储介质
ZHAO XUNGANG (Autor:in) / LI YI (Autor:in) / WANG XIONGJUE (Autor:in) / CHAI XIAOPENG (Autor:in) / LI YANZHE (Autor:in) / ZHA DAOHONG (Autor:in) / ZHAO ZILONG (Autor:in) / WANG BO (Autor:in) / PENG XUMIN (Autor:in) / WANG XIANG (Autor:in)
04.06.2024
Patent
Elektronische Ressource
Chinesisch
Parallel four-main-cable cable-crossing crane and using method thereof
Europäisches Patentamt | 2021
|Pilot cable construction method for erecting main cable of ultra-deep valley cable crane
Europäisches Patentamt | 2020
|Cable crane main cable and anchorage prestress anchoring connecting device and construction method
Europäisches Patentamt | 2021
|Large-span railway suspension bridge cable crane main tower cable saddle construction method
Europäisches Patentamt | 2023
|Cable crane convenient to mount and mounting method of cable crane
Europäisches Patentamt | 2020
|