Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Floating crescent roof structure and construction method thereof
The construction method of the floating crescent roof structure comprises the following steps that firstly, stand columns are constructed, specifically, a set of stand columns are constructed along an arc line according to a design drawing; step 2, constructing arc steel box girders: constructing the arc steel box girders at the tops of one group of upright posts, and connecting the construction arc steel box girders with the upright posts. And thirdly, a set of three-chord trusses are connected to the inner side face of the arc steel box girder at intervals. And fourthly, an inner ring beam is connected to the inner ends of the three-chord trusses, and the two ends of the inner ring beam are connected with the two ends of the arc steel box beam. And fifthly, a top film and side films are constructed, and construction is finished after the top film and the side films are installed. The technical problems that a traditional stadium roof is single in appearance, not beneficial to space utilization and easy to uncover under the wind load are solved.
一种漂浮月牙形屋盖结构及其施工方法,包括步骤如下:步骤一,施工立柱:按照设计图纸,沿弧形线施工一组立柱。步骤二,施工弧线钢箱梁:在一组立柱的顶部施工施工弧线钢箱梁,并将施工弧线钢箱梁与立柱连接。步骤三,将一组三弦桁架间隔连接在弧线钢箱梁的内侧面上。步骤四,将内环梁连接在一组三弦桁架的内端,并且将内环梁的两端与弧线钢箱梁的两端连接。步骤五,施工顶膜和侧膜,待顶膜和侧膜安装完毕,施工结束。本发明解决了传统的体育场屋盖存在的外观单一、不利于空间利用以及在风荷载下容易被揭开的技术问题。
Floating crescent roof structure and construction method thereof
The construction method of the floating crescent roof structure comprises the following steps that firstly, stand columns are constructed, specifically, a set of stand columns are constructed along an arc line according to a design drawing; step 2, constructing arc steel box girders: constructing the arc steel box girders at the tops of one group of upright posts, and connecting the construction arc steel box girders with the upright posts. And thirdly, a set of three-chord trusses are connected to the inner side face of the arc steel box girder at intervals. And fourthly, an inner ring beam is connected to the inner ends of the three-chord trusses, and the two ends of the inner ring beam are connected with the two ends of the arc steel box beam. And fifthly, a top film and side films are constructed, and construction is finished after the top film and the side films are installed. The technical problems that a traditional stadium roof is single in appearance, not beneficial to space utilization and easy to uncover under the wind load are solved.
一种漂浮月牙形屋盖结构及其施工方法,包括步骤如下:步骤一,施工立柱:按照设计图纸,沿弧形线施工一组立柱。步骤二,施工弧线钢箱梁:在一组立柱的顶部施工施工弧线钢箱梁,并将施工弧线钢箱梁与立柱连接。步骤三,将一组三弦桁架间隔连接在弧线钢箱梁的内侧面上。步骤四,将内环梁连接在一组三弦桁架的内端,并且将内环梁的两端与弧线钢箱梁的两端连接。步骤五,施工顶膜和侧膜,待顶膜和侧膜安装完毕,施工结束。本发明解决了传统的体育场屋盖存在的外观单一、不利于空间利用以及在风荷载下容易被揭开的技术问题。
Floating crescent roof structure and construction method thereof
一种漂浮月牙形屋盖结构及其施工方法
LIU SHAOKUI (Autor:in) / WANG YANG (Autor:in) / WANG JI (Autor:in) / ZHANG ZHONGHAO (Autor:in) / AN XIONGBAO (Autor:in) / CHEN HAO (Autor:in) / MA ZECHEN (Autor:in) / XIU RUIXUE (Autor:in) / WANG HAN (Autor:in) / CHEN ZHENGYU (Autor:in)
23.07.2024
Patent
Elektronische Ressource
Chinesisch
Outdoor sunken floating platform roof structure and construction method thereof
Europäisches Patentamt | 2020
|Equipment floating foundation structure for roof and construction method
Europäisches Patentamt | 2024
|Crescent hanging basket suspension support system and construction method thereof
Europäisches Patentamt | 2023
|