Hole-opening-free construction method for whole plate formwork of shear wall
A whole-board formwork-erecting trepanning-free construction method for a shear wall is characterized by comprising the following steps that a, a plurality of battens with the width of 100 mm are manufactured, b, whole-board installation is conducted on the inner side of the shear wall, c, whole-board installation is conducted on the outer side of the shear wall, d, transverse main keels are installed on the inner side and the outer side of the shear wall, opposite-pull screws are installed in matched bolt holes, and d, the transverse main keels are installed on the outer side of the shear wall. The formworks on the inner side and the outer side of the shear wall are fastened; and e, correcting the perpendicularity of the wall body. The hole-opening-free construction method for formwork erecting of the whole plate of the shear wall has the advantages that formwork installation is convenient and fast, the construction period is shortened, the corner damage rate is low, formwork integrity protection is good, secondary turnover can be achieved whether the formwork is used on the wall or the plate, the service life of the formwork can be brought into full play, social resources are saved to the maximum extent, the project cost is reduced, and the construction period is shortened. The common quality problems such as mortar leakage and pitted surfaces are reduced, the flatness and perpendicularity of the wall are guaranteed, and the overall appearance is good.
一种剪力墙整板支模免开孔施工方法,其特征在于包括以下步骤:a、制作若干100mm宽的板条,b、在剪力墙内侧用整板安装,c、在剪力墙外侧用整板安装,d、在剪力墙内侧和外侧安装横向主龙骨,在相配合的螺栓孔中安装对拉螺杆,紧固剪力墙内侧和外侧模板;e、校正墙体垂直度。本发明的剪力墙整板支模免开孔施工方法具有安装模板方便、快捷,缩短工期,棱角破损率低,模板整体性保护的好,二次周转无论用在墙或板上均可,能将模板寿命发挥至极致,最大限度的节约了社会资源,降低项目成本,减少漏浆、麻面等质量通病,保证墙体平整度与垂直度和整体观感好的优点。
Hole-opening-free construction method for whole plate formwork of shear wall
A whole-board formwork-erecting trepanning-free construction method for a shear wall is characterized by comprising the following steps that a, a plurality of battens with the width of 100 mm are manufactured, b, whole-board installation is conducted on the inner side of the shear wall, c, whole-board installation is conducted on the outer side of the shear wall, d, transverse main keels are installed on the inner side and the outer side of the shear wall, opposite-pull screws are installed in matched bolt holes, and d, the transverse main keels are installed on the outer side of the shear wall. The formworks on the inner side and the outer side of the shear wall are fastened; and e, correcting the perpendicularity of the wall body. The hole-opening-free construction method for formwork erecting of the whole plate of the shear wall has the advantages that formwork installation is convenient and fast, the construction period is shortened, the corner damage rate is low, formwork integrity protection is good, secondary turnover can be achieved whether the formwork is used on the wall or the plate, the service life of the formwork can be brought into full play, social resources are saved to the maximum extent, the project cost is reduced, and the construction period is shortened. The common quality problems such as mortar leakage and pitted surfaces are reduced, the flatness and perpendicularity of the wall are guaranteed, and the overall appearance is good.
一种剪力墙整板支模免开孔施工方法,其特征在于包括以下步骤:a、制作若干100mm宽的板条,b、在剪力墙内侧用整板安装,c、在剪力墙外侧用整板安装,d、在剪力墙内侧和外侧安装横向主龙骨,在相配合的螺栓孔中安装对拉螺杆,紧固剪力墙内侧和外侧模板;e、校正墙体垂直度。本发明的剪力墙整板支模免开孔施工方法具有安装模板方便、快捷,缩短工期,棱角破损率低,模板整体性保护的好,二次周转无论用在墙或板上均可,能将模板寿命发挥至极致,最大限度的节约了社会资源,降低项目成本,减少漏浆、麻面等质量通病,保证墙体平整度与垂直度和整体观感好的优点。
Hole-opening-free construction method for whole plate formwork of shear wall
一种剪力墙整板支模免开孔施工方法
ZHAO PENGFEI (Autor:in) / LU BIN (Autor:in) / ZHANG MINGQIANG (Autor:in)
30.07.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Hole-opening-free method for basement shear wall formwork
Europäisches Patentamt | 2022
|Shear wall formwork hole-free reinforcing structure and construction process
Europäisches Patentamt | 2020
|CL shear wall formwork whole-piece construction assembling method
Europäisches Patentamt | 2022
|Formwork-free shear wall and construction method thereof
Europäisches Patentamt | 2015
|