Construction method of prefabricated reverse ridge
The invention discloses a construction method of a prefabricated reverse ridge. The construction method comprises the following steps: 1, prefabricating and processing a reverse ridge main body; 2, a plurality of positioning ribs are pre-buried in the reverse ridge construction area at intervals; 3, a waterproof layer is constructed in the reverse ridge construction area, and a plurality of positioning ribs penetrate through the waterproof layer; 4, the bottom of the reverse ridge body is placed in the waterproof layer, and the multiple positioning ribs are inserted into the positioning holes; and 5, mortar is injected into the reverse sill body, so that the reverse sill body, the waterproof layer and the building component are connected into a whole. The invention relates to the technical field of building construction, and can solve the problems that in the prior art, a one-time poured reverse ridge has positioning deviation, and the reverse ridge subjected to chiseling pouring construction is prone to leakage.
本发明公开了一种预制反坎的施工方法,包括步骤:1:预制加工反坎主体;2:在反坎施工区域内间隔预埋若干根定位筋;3:在反坎施工区域内施工防水层,若干根定位筋贯穿防水层;4:将反坎主体的底部置于防水层内,且使若干根定位筋插入在定位孔内;5:向反坎主体内注入砂浆,使反坎主体和防水层与建筑构件连接形成一个整体。本发明涉及建筑施工技术领域,能够解决现有技术中一次性浇筑的反坎存在定位偏差、凿毛浇筑施工的反坎容易渗漏的问题。
Construction method of prefabricated reverse ridge
The invention discloses a construction method of a prefabricated reverse ridge. The construction method comprises the following steps: 1, prefabricating and processing a reverse ridge main body; 2, a plurality of positioning ribs are pre-buried in the reverse ridge construction area at intervals; 3, a waterproof layer is constructed in the reverse ridge construction area, and a plurality of positioning ribs penetrate through the waterproof layer; 4, the bottom of the reverse ridge body is placed in the waterproof layer, and the multiple positioning ribs are inserted into the positioning holes; and 5, mortar is injected into the reverse sill body, so that the reverse sill body, the waterproof layer and the building component are connected into a whole. The invention relates to the technical field of building construction, and can solve the problems that in the prior art, a one-time poured reverse ridge has positioning deviation, and the reverse ridge subjected to chiseling pouring construction is prone to leakage.
本发明公开了一种预制反坎的施工方法,包括步骤:1:预制加工反坎主体;2:在反坎施工区域内间隔预埋若干根定位筋;3:在反坎施工区域内施工防水层,若干根定位筋贯穿防水层;4:将反坎主体的底部置于防水层内,且使若干根定位筋插入在定位孔内;5:向反坎主体内注入砂浆,使反坎主体和防水层与建筑构件连接形成一个整体。本发明涉及建筑施工技术领域,能够解决现有技术中一次性浇筑的反坎存在定位偏差、凿毛浇筑施工的反坎容易渗漏的问题。
Construction method of prefabricated reverse ridge
预制反坎的施工方法
GUO YACHAO (Autor:in) / HUANG ZHENYU (Autor:in) / ZHANG SHAOZE (Autor:in) / CAI TIANYU (Autor:in) / ZHAO ZILONG (Autor:in)
06.12.2024
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2023
|Prefabricated toilet descending plate structure with reverse ridge
Europäisches Patentamt | 2023
|Concrete reverse ridge accurate positioning mold and reverse ridge construction method
Europäisches Patentamt | 2021
|Construction method for preposed prefabricated concrete water stop ridge
Europäisches Patentamt | 2023
|