CONSTRUCTION METHOD FOR SCOURING PREVENTION STRUCTURE
To provide a construction method for a scouring prevention structure which enables safe and efficient installation of a stone crushing unit.SOLUTION: Stone crushing units 21b are suspended from each of a plurality of suspending wires 35 connected to a suspending jig 29c. The stone crushing units 21b are suspended so as to mutually overlap in plan view and have mutually different suspending heights. The suspending jig 29c is suspended by a crane 7, and the stone crushing unit 21b is installed in an underwater ground 1 so that the adjacent stone crushing units 21b mutually overlap. At this time, a deviation between management positions 221b of the stone crushing units 21b grasped by acquiring a position of a crane ship 5 by a GPS antenna 13 and actual positions of the stone crushing units 21b and the suspending jig 29c under the water grasped by an underwater sonar 15 of the crane ship 5 is confirmed, and the positions are aligned.SELECTED DRAWING: Figure 14
【課題】砕石ユニットを安全且つ効率的に設置することができる洗掘防止工の施工方法を提供する。【解決手段】吊り治具29cに接続された複数の吊下げワイヤ35のそれぞれに砕石ユニット21bを吊り下げる。砕石ユニット21bは、平面視において互いに重なり合うように且つ吊り高さが互いに異なるように吊り下げられる。そして、吊り治具29cを揚重機7によって吊り下ろし、隣り合う砕石ユニット21b同士が互いに重なり合うように砕石ユニット21bを水中地盤1に設置する。このとき、GPSアンテナ13で起重機船5の位置を取得して把握した砕石ユニット21bの管理位置221bと、起重機船5の水中ソナー15で把握した水中の砕石ユニット21bや吊り治具29cの実際の位置とのずれを確認して位置合わせをする。【選択図】図14
CONSTRUCTION METHOD FOR SCOURING PREVENTION STRUCTURE
To provide a construction method for a scouring prevention structure which enables safe and efficient installation of a stone crushing unit.SOLUTION: Stone crushing units 21b are suspended from each of a plurality of suspending wires 35 connected to a suspending jig 29c. The stone crushing units 21b are suspended so as to mutually overlap in plan view and have mutually different suspending heights. The suspending jig 29c is suspended by a crane 7, and the stone crushing unit 21b is installed in an underwater ground 1 so that the adjacent stone crushing units 21b mutually overlap. At this time, a deviation between management positions 221b of the stone crushing units 21b grasped by acquiring a position of a crane ship 5 by a GPS antenna 13 and actual positions of the stone crushing units 21b and the suspending jig 29c under the water grasped by an underwater sonar 15 of the crane ship 5 is confirmed, and the positions are aligned.SELECTED DRAWING: Figure 14
【課題】砕石ユニットを安全且つ効率的に設置することができる洗掘防止工の施工方法を提供する。【解決手段】吊り治具29cに接続された複数の吊下げワイヤ35のそれぞれに砕石ユニット21bを吊り下げる。砕石ユニット21bは、平面視において互いに重なり合うように且つ吊り高さが互いに異なるように吊り下げられる。そして、吊り治具29cを揚重機7によって吊り下ろし、隣り合う砕石ユニット21b同士が互いに重なり合うように砕石ユニット21bを水中地盤1に設置する。このとき、GPSアンテナ13で起重機船5の位置を取得して把握した砕石ユニット21bの管理位置221bと、起重機船5の水中ソナー15で把握した水中の砕石ユニット21bや吊り治具29cの実際の位置とのずれを確認して位置合わせをする。【選択図】図14
CONSTRUCTION METHOD FOR SCOURING PREVENTION STRUCTURE
洗掘防止構造の施工方法
UMEZU ISSEI (Autor:in) / FUJITA HIDEHIRO (Autor:in) / USAMI EIJI (Autor:in)
27.01.2022
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
SCOURING PREVENTION STRUCTURE, AND CONSTRUCTION METHOD OF SCOURING PREVENTION STRUCTURE
Europäisches Patentamt | 2023
|SCOURING PREVENTION STRUCTURE AND SCOURING PREVENTION METHOD
Europäisches Patentamt | 2022
|SCOURING PREVENTION UNIT AND SCOURING PREVENTION STRUCTURE
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2024
|SCOURING PREVENTION BODY AND SCOURING PREVENTION METHOD
Europäisches Patentamt | 2023
|