CONSTRUCTION METHOD OF BLOCK PAVEMENT BODY
To provide a construction method of block pavement bodies which reduces the burden of conveying blocks by field workers and increases construction efficiency at construction sites.SOLUTION: Provided is a construction method of block pavement bodies which constructs block pavement bodies using multiple types of blocks, and in which the following process a, process b, and process c are carried out at least for the blocks initially delivered to a construction site. Process a: pallet preparing process in which multiple types of blocks are placed on a pallet, and the blocks are rearranged such that the number of stairs of each block type corresponds to the usage ratio of each block type at the construction site; process b in which pallets loaded with rearranged blocks types are conveyed to the construction site and placed in a block storage area at the construction site; process c in which blocks are taken out from the pallets loaded with rearranged blocks types and paved at the construction site.SELECTED DRAWING: Figure 2
【課題】現場作業員によるブロックの運搬作業の負担を軽減し、施工現場での施工効率を高めるブロック舗装体の施工方法を提供すること。【解決手段】複数種のブロックを用いてブロック舗装体を施工するブロック舗装体の施工方法であって、下記の工程a、工程b、及び工程cを少なくとも施工現場に最初に納品するブロックについて実施することを特徴とするブロック舗装体の施工方法。工程a:パレット上に、前記複数種のブロックを、各種ブロックのそれぞれの段数が前記施工現場での各種ブロックのそれぞれの使用比率に対応する段数となるように前記ブロックを載置してなるブロックを組み換えたパレットを準備する工程、工程b:前記ブロックを組み換えたパレットを前記施工現場に搬送し、前記施工現場のブロック置き場に配置する工程、工程c:前記ブロックを組み換えたパレットからブロックを取り出して前記施工現場で舗装作業を行う工程【選択図】図2
CONSTRUCTION METHOD OF BLOCK PAVEMENT BODY
To provide a construction method of block pavement bodies which reduces the burden of conveying blocks by field workers and increases construction efficiency at construction sites.SOLUTION: Provided is a construction method of block pavement bodies which constructs block pavement bodies using multiple types of blocks, and in which the following process a, process b, and process c are carried out at least for the blocks initially delivered to a construction site. Process a: pallet preparing process in which multiple types of blocks are placed on a pallet, and the blocks are rearranged such that the number of stairs of each block type corresponds to the usage ratio of each block type at the construction site; process b in which pallets loaded with rearranged blocks types are conveyed to the construction site and placed in a block storage area at the construction site; process c in which blocks are taken out from the pallets loaded with rearranged blocks types and paved at the construction site.SELECTED DRAWING: Figure 2
【課題】現場作業員によるブロックの運搬作業の負担を軽減し、施工現場での施工効率を高めるブロック舗装体の施工方法を提供すること。【解決手段】複数種のブロックを用いてブロック舗装体を施工するブロック舗装体の施工方法であって、下記の工程a、工程b、及び工程cを少なくとも施工現場に最初に納品するブロックについて実施することを特徴とするブロック舗装体の施工方法。工程a:パレット上に、前記複数種のブロックを、各種ブロックのそれぞれの段数が前記施工現場での各種ブロックのそれぞれの使用比率に対応する段数となるように前記ブロックを載置してなるブロックを組み換えたパレットを準備する工程、工程b:前記ブロックを組み換えたパレットを前記施工現場に搬送し、前記施工現場のブロック置き場に配置する工程、工程c:前記ブロックを組み換えたパレットからブロックを取り出して前記施工現場で舗装作業を行う工程【選択図】図2
CONSTRUCTION METHOD OF BLOCK PAVEMENT BODY
ブロック舗装体の施工方法
SUZUKI NOBUAKI (Autor:in)
30.05.2023
Patent
Elektronische Ressource
Japanisch
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
PAVEMENT MATERIAL, PAVEMENT BODY, AND PAVEMENT BODY CONSTRUCTION METHOD
Europäisches Patentamt | 2021
|BLOCK PAVEMENT METHOD, BLOCK PAVEMENT STRUCTURE AND PAVEMENT BLOCK
Europäisches Patentamt | 2023
|BLOCK PAVEMENT METHOD, BLOCK PAVEMENT STRUCTURE, AND BLOCK PAVEMENT REINFORCEMENT PLATE
Europäisches Patentamt | 2020
|BLOCK PAVEMENT STRUCTURE AND CONSTRUCTION METHOD THEREOF
Europäisches Patentamt | 2017
|