JOINING METHOD OF COMPOSITE FLOOR SLAB
To provide a joining method of a composite floor slab capable of performing work for connecting bottom plates of the composite floor slab to each other by bolts without installing a scaffold.SOLUTION: The end sides of first reinforcing bars 12 of a composite floor slab 10 adjacent to each other are arranged so that bolts 16 are positioned below parts between the first reinforcing bars 12, and since bottom plates 11 are connected to each other by fastening nuts 16b to the bolts 16 temporarily fixed to the bottom plate 11 in advance from above through between the first reinforcing bars 12, the fastening work of the nuts 16b can be performed from above the bottom plates 11. In this case, the first reinforcing bars 12 of one composite floor slab 10 and the first reinforcing bars 12 of the other composite floor slab 10 are arranged so that a wide interval A1 and a narrow interval A2 are alternately formed, and the bolts 16 are positioned below the wide interval A1, so that a space for fastening work of nuts from between the reinforcing bars can be sufficiently secured.SELECTED DRAWING: Figure 2
【課題】足場を設置することなく合成床版の底板同士をボルトで連結する作業を行うことのできる合成床版の接合方法を提供する。【解決手段】互いに隣り合う合成床版10の第1の鉄筋12の端部側を、各第1の鉄筋12の間部分の下方にボルト16が位置するように配置し、予め底板11に仮固定しておいたボルト16に第1の鉄筋12の間を通して上方からナット16bを締結することにより底板11同士を連結するようにしたので、ナット16bの締結作業を底板11の上方から行うことができる。その際、一方の合成床版10の第1の鉄筋12と他方の合成床版10の第1の鉄筋12とを、広い間隔A1 と狭い間隔A2 が一つおきに交互に形成されるように配置するとともに、広い間隔A1 の下方にボルト16が位置するようにしたので、鉄筋の間からナットの締結作業を行うためのスペースを十分に確保することができる。【選択図】図2
JOINING METHOD OF COMPOSITE FLOOR SLAB
To provide a joining method of a composite floor slab capable of performing work for connecting bottom plates of the composite floor slab to each other by bolts without installing a scaffold.SOLUTION: The end sides of first reinforcing bars 12 of a composite floor slab 10 adjacent to each other are arranged so that bolts 16 are positioned below parts between the first reinforcing bars 12, and since bottom plates 11 are connected to each other by fastening nuts 16b to the bolts 16 temporarily fixed to the bottom plate 11 in advance from above through between the first reinforcing bars 12, the fastening work of the nuts 16b can be performed from above the bottom plates 11. In this case, the first reinforcing bars 12 of one composite floor slab 10 and the first reinforcing bars 12 of the other composite floor slab 10 are arranged so that a wide interval A1 and a narrow interval A2 are alternately formed, and the bolts 16 are positioned below the wide interval A1, so that a space for fastening work of nuts from between the reinforcing bars can be sufficiently secured.SELECTED DRAWING: Figure 2
【課題】足場を設置することなく合成床版の底板同士をボルトで連結する作業を行うことのできる合成床版の接合方法を提供する。【解決手段】互いに隣り合う合成床版10の第1の鉄筋12の端部側を、各第1の鉄筋12の間部分の下方にボルト16が位置するように配置し、予め底板11に仮固定しておいたボルト16に第1の鉄筋12の間を通して上方からナット16bを締結することにより底板11同士を連結するようにしたので、ナット16bの締結作業を底板11の上方から行うことができる。その際、一方の合成床版10の第1の鉄筋12と他方の合成床版10の第1の鉄筋12とを、広い間隔A1 と狭い間隔A2 が一つおきに交互に形成されるように配置するとともに、広い間隔A1 の下方にボルト16が位置するようにしたので、鉄筋の間からナットの締結作業を行うためのスペースを十分に確保することができる。【選択図】図2
JOINING METHOD OF COMPOSITE FLOOR SLAB
合成床版の接合方法
SUZUKI OSAMU (Autor:in) / SUETSUGU TAKESHI (Autor:in) / FUKUI ATSUSHI (Autor:in) / TAKAI YUSUKE (Autor:in) / KISAKU TOMOAKI (Autor:in) / YOSHIDA YUKI (Autor:in) / NIE JING (Autor:in)
19.03.2024
Patent
Elektronische Ressource
Japanisch
IPC:
E01D
BRIDGES
,
Brücken
JOINING METHOD OF PRECAST FLOOR SLAB AND JOINING STRUCTURE OF PRECAST FLOOR SLAB
Europäisches Patentamt | 2017
|FLOOR SLAB RENEWAL METHOD, FLOOR SLAB JOINING STRUCTURE AND ROAD BRIDGE