Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
PARTIAL PREFLEXION COMPOSITE GIRDER AND COLUMN CONNECTION STRUCTURE CONSTRUCTION METHOD AND GIRDER AND COLUMN CONNECTION STRUCTURE CONSTRUCTED THEREBY
A method of constructing a connection structure between a partial reflection composite girder and a column is disclosed. According to the present invention, the method of constructing a connection structure of a partial reflection composite girder and a column comprises: a first construction step of preparing a partial reflection composite girder by combining a socket reinforcement member at the center of the girder where sagging occurs; a second construction step of setting and fixing foundation columns in the foundation; a third construction step of installing a first cover-type connection part on the top of the foundation column; a fourth construction step of connecting the partial reflection composite girders to the first cover-type connection part, and providing a second cover-type connection part at the top of the foundation column or a lower part of the upper column to connect the foundation column and the partial reflection composite girder; and a fifth construction step of placing deck plates and slab rebar on the floor where the partial reflection composite girders are installed, followed by pouring concrete.
부분 프리플렉션 합성 거더와 기둥의 연결구조 시공방법이 개시된다. 본 발명에 따른 부분 프리플렉션 합성 거더와 기둥의 연결구조 시공방법은, 처짐이 발생한 거더의 중앙부에 소켓 보강부재를 결합하여 부분 프리플렉션 합성 거더를 마련하는 제1 시공단계, 기초부에 기초 기둥을 세팅하고 고정하는 제2 시공단계, 기초 기둥의 상부에 제1 커버형 연결부를 설치하는 제3 시공단계, 제1 커버형 연결부에 부분 프리플렉션 합성 거더를 각각 연결하고, 기초 기둥 최상부 또는 상층 기둥의 하부에 제2 커버형 연결부를 마련하여 기초 기둥과 부분 프리플렉션 합성 거더를 연결하는 제4 시공단계, 및 부분 프리플렉션 합성 거더가 설치된 층에 데크플레이트와 슬래브 철근을 배근한 후 콘크리트를 타설하는 제5 시공단계를 포함한다.
PARTIAL PREFLEXION COMPOSITE GIRDER AND COLUMN CONNECTION STRUCTURE CONSTRUCTION METHOD AND GIRDER AND COLUMN CONNECTION STRUCTURE CONSTRUCTED THEREBY
A method of constructing a connection structure between a partial reflection composite girder and a column is disclosed. According to the present invention, the method of constructing a connection structure of a partial reflection composite girder and a column comprises: a first construction step of preparing a partial reflection composite girder by combining a socket reinforcement member at the center of the girder where sagging occurs; a second construction step of setting and fixing foundation columns in the foundation; a third construction step of installing a first cover-type connection part on the top of the foundation column; a fourth construction step of connecting the partial reflection composite girders to the first cover-type connection part, and providing a second cover-type connection part at the top of the foundation column or a lower part of the upper column to connect the foundation column and the partial reflection composite girder; and a fifth construction step of placing deck plates and slab rebar on the floor where the partial reflection composite girders are installed, followed by pouring concrete.
부분 프리플렉션 합성 거더와 기둥의 연결구조 시공방법이 개시된다. 본 발명에 따른 부분 프리플렉션 합성 거더와 기둥의 연결구조 시공방법은, 처짐이 발생한 거더의 중앙부에 소켓 보강부재를 결합하여 부분 프리플렉션 합성 거더를 마련하는 제1 시공단계, 기초부에 기초 기둥을 세팅하고 고정하는 제2 시공단계, 기초 기둥의 상부에 제1 커버형 연결부를 설치하는 제3 시공단계, 제1 커버형 연결부에 부분 프리플렉션 합성 거더를 각각 연결하고, 기초 기둥 최상부 또는 상층 기둥의 하부에 제2 커버형 연결부를 마련하여 기초 기둥과 부분 프리플렉션 합성 거더를 연결하는 제4 시공단계, 및 부분 프리플렉션 합성 거더가 설치된 층에 데크플레이트와 슬래브 철근을 배근한 후 콘크리트를 타설하는 제5 시공단계를 포함한다.
PARTIAL PREFLEXION COMPOSITE GIRDER AND COLUMN CONNECTION STRUCTURE CONSTRUCTION METHOD AND GIRDER AND COLUMN CONNECTION STRUCTURE CONSTRUCTED THEREBY
부분 프리플렉션 합성 거더와 기둥의 연결구조 시공방법 및 이에 의해 시공된 거더와 기둥의 연결구조
JEONG HAE YOUNG (Autor:in)
11.01.2024
Patent
Elektronische Ressource
Koreanisch
Europäisches Patentamt | 2024
|- Connection Structure of Column and Steel-Concrete Composite Girder
Europäisches Patentamt | 2018
|Europäisches Patentamt | 2015
|Hinge connection structure of steel box girder and steel box girder connection construction method
Europäisches Patentamt | 2024
|Connection joint and connection method for box girder and box column
Europäisches Patentamt | 2015
|