CONSTRUCTION METHOD OF MULTI PREFLEX COMPOSITE GIRDER
Disclosed is a construction method of a multi-preflex composite girder which uses a restoring force of a steel beam to introduce prestress to casing concrete. The construction method of a multi-preflex composite girder comprises: a steel beam mounting step of mounting a front and a rear end of a steel beam whose longitudinal middle portion is cambered upwards on a support; a temporary reinforcing plate installation step of fixing a temporary reinforcing plate in a longitudinal direction of an upper plate of the steel beam to bring the temporary reinforcing plate into surface contact with the upper plate; a preflexion load applying step of applying a preflexion load to the temporary reinforcing plate and the steel beam; a casing concrete deposition step of installing casing concrete on a lower plate of the steel beam; a preflexion load removal step of removing the preflexion load applied to the temporary reinforcing plate and the steel beam; and a temporary reinforcing plate separation step of separating the temporary reinforcing plate from the steel beam. According to the present invention, since additional compressive stress is introduced to the casing concrete by the temporary reinforcing plate, the amount of steel used in an upper plate of an I-shaped steel beam can be reduced. Therefore, construction costs can be reduced.
강재빔의 복원력을 이용하여 케이싱 콘크리트에 프리스트레스를 도입하는 복합 프리플렉스 강합성 거더의 시공방법이 개시된다. 이를 위하여 길이 방향을 기준으로 중앙부가 상방으로 솟음 처리된 강재빔의 선단 및 후단을 지지대에 거치하는 강재빔 거치단계와, 상기 강재빔의 상부플레이트에 접면되도록 임시보강판을 상기 상부플레이트의 길이방향을 따라 고정시키는 임시보강판 설치단계와, 상기 임시보강판 및 강재빔에 프리플렉션 하중을 가하는 프리플렉션 하중 재하단계와, 상기 강재빔의 하부플레이트에 케이싱 콘크리트를 설치하는 케이싱 콘크리트 타설단계와, 상기 임시보강판 및 강재빔에 재하된 프리플렉션 하중을 제거하는 프리플렉션 하중 제거단계, 및 상기 임시보강판을 상기 강재빔으로부터 분리하는 임시보강판 분리단계를 포함하는 복합 프리플렉스 강합성 거더의 시공방법을 제공한다. 본 발명에 의하면, 임시보강판에 의해 케이싱 콘크리트에 추가 압축응력이 도입되는 만큼 I형 강재빔의 상부플레이트에 사용된 강재량을 감소시킬 수 있으므로, 공사비용을 절감시킬 수 있다.
CONSTRUCTION METHOD OF MULTI PREFLEX COMPOSITE GIRDER
Disclosed is a construction method of a multi-preflex composite girder which uses a restoring force of a steel beam to introduce prestress to casing concrete. The construction method of a multi-preflex composite girder comprises: a steel beam mounting step of mounting a front and a rear end of a steel beam whose longitudinal middle portion is cambered upwards on a support; a temporary reinforcing plate installation step of fixing a temporary reinforcing plate in a longitudinal direction of an upper plate of the steel beam to bring the temporary reinforcing plate into surface contact with the upper plate; a preflexion load applying step of applying a preflexion load to the temporary reinforcing plate and the steel beam; a casing concrete deposition step of installing casing concrete on a lower plate of the steel beam; a preflexion load removal step of removing the preflexion load applied to the temporary reinforcing plate and the steel beam; and a temporary reinforcing plate separation step of separating the temporary reinforcing plate from the steel beam. According to the present invention, since additional compressive stress is introduced to the casing concrete by the temporary reinforcing plate, the amount of steel used in an upper plate of an I-shaped steel beam can be reduced. Therefore, construction costs can be reduced.
강재빔의 복원력을 이용하여 케이싱 콘크리트에 프리스트레스를 도입하는 복합 프리플렉스 강합성 거더의 시공방법이 개시된다. 이를 위하여 길이 방향을 기준으로 중앙부가 상방으로 솟음 처리된 강재빔의 선단 및 후단을 지지대에 거치하는 강재빔 거치단계와, 상기 강재빔의 상부플레이트에 접면되도록 임시보강판을 상기 상부플레이트의 길이방향을 따라 고정시키는 임시보강판 설치단계와, 상기 임시보강판 및 강재빔에 프리플렉션 하중을 가하는 프리플렉션 하중 재하단계와, 상기 강재빔의 하부플레이트에 케이싱 콘크리트를 설치하는 케이싱 콘크리트 타설단계와, 상기 임시보강판 및 강재빔에 재하된 프리플렉션 하중을 제거하는 프리플렉션 하중 제거단계, 및 상기 임시보강판을 상기 강재빔으로부터 분리하는 임시보강판 분리단계를 포함하는 복합 프리플렉스 강합성 거더의 시공방법을 제공한다. 본 발명에 의하면, 임시보강판에 의해 케이싱 콘크리트에 추가 압축응력이 도입되는 만큼 I형 강재빔의 상부플레이트에 사용된 강재량을 감소시킬 수 있으므로, 공사비용을 절감시킬 수 있다.
CONSTRUCTION METHOD OF MULTI PREFLEX COMPOSITE GIRDER
복합 프리플렉스 강합성 거더의 시공방법
HA SEUNG UK (Autor:in)
13.11.2019
Patent
Elektronische Ressource
Koreanisch
IPC:
E01D
BRIDGES
,
Brücken
Europäisches Patentamt | 2016
|preflex steel girder manufacturing apparatus and preflex steel girder manufacturing method
Europäisches Patentamt | 2017
|Europäisches Patentamt | 2021
|The manufacturing method of preflex steel girder and a preflex steel girder manufactured by the same
Europäisches Patentamt | 2017
|