Foundation construction structure for retaining and its construction method
The present invention aims to provide a foundation structure for retaining soil and a construction method thereof, which can maximize the resistance to earth pressure more easily than before by constructing a retaining beam, a reinforcing beam, and a truss beam, thereby shortening the construction period and reducing material consumption for foundation construction including excavation construction and retaining soil construction, and securing a work space for construction. The foundation structure for retaining soil of the present invention includes: a retaining beam (100) that is installed vertically by being drilled into a first perforation hole (30a) formed at a predetermined distance in the back ground (20) along the circumference of the excavated ground (10) to be excavated for installation of a retaining soil for retaining soil construction; a reinforcing beam (200) that is installed vertically by being drilled into a second perforation hole (30b) formed at a predetermined distance corresponding to the first perforation hole (30a); and a truss beam (300) that is installed continuously at intervals along the vertical length direction of the reinforcing beam (200) and horizontally forgets the reinforcing beam (200) and the earth retaining beam (100). By providing the present invention configured as described above, the construction period of foundation work including excavation work and earth retaining work can be shortened and material consumption can be reduced, and there is an effect of securing a work space for construction.
본 발명은 흙막이를 위한 기초공사 구조물 및 그 시공방법에 관한 것으로, 신축공사 현장에서 터파기 되는 굴착지반의 둘레를 따라 흙막이 시공을 위한 흙막이의 설치를 위해 배면지반에 소정의 거리를 두고 천공 형성된 제1천공홀에 근입되어 수직으로 설치되는 흙막이빔과; 제1천공홀에 대응하여 소정의 거리를 두고 천공 형성된 제2천공홀에 근입되어 수직으로 설치되는 보강빔과; 보강빔에 수직의 길이 방향을 따라 간격을 두고 연속적으로 설치되며, 보강빔과 흙막이빔을 수평으로 잊는 트러스빔을 포함하는 것을 특징으로 하는 흙막이를 위한 기초공사 구조물을 제공하고, 천공기를 통해 건축물의 시공을 위해 터파기 공사되는 굴착지반의 테두리를 따라 흙막이 설치를 위한 흙막이빔을 설정된 거리로 배열을 위해 배면지반에 대응되는 수직 방향으로 설정된 거리를 두고 다수의 제1천공홀을 천공 형성하는 제1천공단계와; 흙막이빔에 대응하여 동일한 간격을 두고 보강빔을 수직으로 설치할 수 있도록 천공기를 통해 제1천공홀에 대응하여 설정된 거리를 두고 다수의 제2천공홀을 천공 형성하는 제2천공단계와; 제1천공홀에 흙막이빔을 수직으로 근입 설치하는 제1근입단계와; 제2천공홀에 보강빔을 수직으로 근입 설치하는 제2근입단계와; 보강빔의 허용응력으로 지지되어 토압에 의한 흙막이빔의 기울어짐을 방지할 수 있도록 수직 설치된 흙막이빔 및 보강빔을 수평으로 트러스빔을 설치하는 가설단계와; 굴착지반에 건축물의 기초를 건설하는 건설단계와; 건설되는 건축물의 높이에 따라 트러스빔을 철거하는 철거단계를 포함하는 것을 특징으로 하는 흙막이를 위한 기초공사 구조물 시공방법을 제공하여 터파기 시공 및 흙막이 시공을 포함하는 기초공사의 공기단축 및 자재소모를 절감할 수 있으며, 공사를 위한 작업공간을 확보할 수 있는 흙막이를 위한 기초공사 구조물 및 그 시공방법에 관한 것이다.
Foundation construction structure for retaining and its construction method
The present invention aims to provide a foundation structure for retaining soil and a construction method thereof, which can maximize the resistance to earth pressure more easily than before by constructing a retaining beam, a reinforcing beam, and a truss beam, thereby shortening the construction period and reducing material consumption for foundation construction including excavation construction and retaining soil construction, and securing a work space for construction. The foundation structure for retaining soil of the present invention includes: a retaining beam (100) that is installed vertically by being drilled into a first perforation hole (30a) formed at a predetermined distance in the back ground (20) along the circumference of the excavated ground (10) to be excavated for installation of a retaining soil for retaining soil construction; a reinforcing beam (200) that is installed vertically by being drilled into a second perforation hole (30b) formed at a predetermined distance corresponding to the first perforation hole (30a); and a truss beam (300) that is installed continuously at intervals along the vertical length direction of the reinforcing beam (200) and horizontally forgets the reinforcing beam (200) and the earth retaining beam (100). By providing the present invention configured as described above, the construction period of foundation work including excavation work and earth retaining work can be shortened and material consumption can be reduced, and there is an effect of securing a work space for construction.
본 발명은 흙막이를 위한 기초공사 구조물 및 그 시공방법에 관한 것으로, 신축공사 현장에서 터파기 되는 굴착지반의 둘레를 따라 흙막이 시공을 위한 흙막이의 설치를 위해 배면지반에 소정의 거리를 두고 천공 형성된 제1천공홀에 근입되어 수직으로 설치되는 흙막이빔과; 제1천공홀에 대응하여 소정의 거리를 두고 천공 형성된 제2천공홀에 근입되어 수직으로 설치되는 보강빔과; 보강빔에 수직의 길이 방향을 따라 간격을 두고 연속적으로 설치되며, 보강빔과 흙막이빔을 수평으로 잊는 트러스빔을 포함하는 것을 특징으로 하는 흙막이를 위한 기초공사 구조물을 제공하고, 천공기를 통해 건축물의 시공을 위해 터파기 공사되는 굴착지반의 테두리를 따라 흙막이 설치를 위한 흙막이빔을 설정된 거리로 배열을 위해 배면지반에 대응되는 수직 방향으로 설정된 거리를 두고 다수의 제1천공홀을 천공 형성하는 제1천공단계와; 흙막이빔에 대응하여 동일한 간격을 두고 보강빔을 수직으로 설치할 수 있도록 천공기를 통해 제1천공홀에 대응하여 설정된 거리를 두고 다수의 제2천공홀을 천공 형성하는 제2천공단계와; 제1천공홀에 흙막이빔을 수직으로 근입 설치하는 제1근입단계와; 제2천공홀에 보강빔을 수직으로 근입 설치하는 제2근입단계와; 보강빔의 허용응력으로 지지되어 토압에 의한 흙막이빔의 기울어짐을 방지할 수 있도록 수직 설치된 흙막이빔 및 보강빔을 수평으로 트러스빔을 설치하는 가설단계와; 굴착지반에 건축물의 기초를 건설하는 건설단계와; 건설되는 건축물의 높이에 따라 트러스빔을 철거하는 철거단계를 포함하는 것을 특징으로 하는 흙막이를 위한 기초공사 구조물 시공방법을 제공하여 터파기 시공 및 흙막이 시공을 포함하는 기초공사의 공기단축 및 자재소모를 절감할 수 있으며, 공사를 위한 작업공간을 확보할 수 있는 흙막이를 위한 기초공사 구조물 및 그 시공방법에 관한 것이다.
Foundation construction structure for retaining and its construction method
흙막이를 위한 기초공사 구조물 및 그 시공방법
KIM JAE SIK (Autor:in)
29.12.2023
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile foundation retaining wall structure and construction method
Europäisches Patentamt | 2020
|Retaining structure for foundation pit section construction
Europäisches Patentamt | 2020
|Adjacent foundation pit cooperative construction retaining structure and construction method thereof
Europäisches Patentamt | 2020
|FOUNDATION PIT RETAINING STRUCTURE SYSTEM AND CONSTRUCTION METHOD THEREFOR
Europäisches Patentamt | 2020
|Cofferdam water retaining structure for beach bridge foundation construction and construction method
Europäisches Patentamt | 2023
|