CONSTRUCTION METHOD FOR CONSTRUCTING GATEWAY IN LIMITED SPACE UNDERNEATH BRIDGE
Provided in the present invention is a construction method for constructing a gateway in a limited space underneath a bridge. The construction method comprises the following steps: S1, setting up an appropriate construction location; S2, marking an extension path, construction starting point and construction end point of a gateway; S3, constructing first cast-in-place piles; S4, connecting and fixing the first cast-in-place piles on two sides by means of positioning frames; S5, excavating a first excavation pit and a second excavation pit, and providing second excavation pits on two sides of the gateway in the extension direction; S6, simultaneously constructing a third excavation pit, wherein the first excavation pit, the second excavation pit and the third excavation pit are arranged in a stepped shape; S7, continuing to excavate; S8, repeating S3-S6 until a second foundation pit body is formed; S9, completing the construction of third cast-in-place piles; S10, forming a first communicating foundation pit; S11, repeating S3-S10 until a second communicating foundation pit and continuous cast-in-place piles in rows are completed; and S12, erecting formwork and performing pouring and filling, and thereby forming a designed target pit. The present invention makes construction efficient, can greatly improve the overall construction efficiency, and can also ensure the operation safety.
Est prévu dans la présente invention un procédé de construction pour construire une passerelle dans un espace limité sous un pont. Le procédé de construction comprend les étapes suivantes consistant à : S1, définir un emplacement de construction approprié ; S2, marquer un trajet d'extension, un point de début de construction et un point de fin de construction d'une passerelle ; S3, construire des premiers pieux coulés sur place ; S4, relier et fixer les premiers pieux coulés sur place sur deux côtés au moyen de cadres de positionnement ; S5, excaver une première fosse d'excavation et une deuxième fosse d'excavation, et fournir des deuxièmes fosses d'excavation sur deux côtés de la passerelle dans la direction d'extension ; S6, construire simultanément une troisième fosse d'excavation, la première fosse d'excavation, la deuxième fosse d'excavation et la troisième fosse d'excavation étant agencées selon une forme étagée ; S7, continuer à excaver ; S8, répéter S3-S6 jusqu'à ce qu'un second corps de fosse de fondation soit formé ; S9, terminer la construction de troisièmes pieux coulés sur place ; S10, former une première fosse de fondation communicante ; S11, répéter S3-S10 jusqu'à ce qu'une seconde fosse de fondation communicante et des pieux coulés sur place continus en rangées soient terminés ; et S12, ériger le coffrage et effectuer un coulage et un remplissage, et former ainsi une fosse cible désignée. La présente invention rend la construction efficace, permet d'améliorer considérablement l'efficacité globale de la construction et également d'assurer la sécurité de fonctionnement.
本发明提供一种下穿桥梁的有限空间内施工闸道的施工方法,包括以下步骤:S1、设置合适的施工位置;S2、标记出闸道的走线路径、施工起点和终点;S3、进行第一灌注桩的施工;S4、两侧的第一灌注桩通过定位架连接固定;S5、开挖第一开挖坑和第二开挖坑,同时在沿闸道的走向两侧设置第二开挖坑;S6、同时进行第三开挖坑的施工,第一开挖坑、第二开挖坑和第三开挖坑成阶梯设置;S7、继续开挖;S8、循环S3~S6,直至形成第二基坑体;S9、完成第三灌注桩的施工;S10、形成第一连通基坑;S11、重复S3~S10,直至完成第二连通基坑和连排灌注桩;S12、立模浇筑填充,形成设计目标坑。本发明施工高效,能大幅度提高整体的施工效率,保证作业安全。
CONSTRUCTION METHOD FOR CONSTRUCTING GATEWAY IN LIMITED SPACE UNDERNEATH BRIDGE
Provided in the present invention is a construction method for constructing a gateway in a limited space underneath a bridge. The construction method comprises the following steps: S1, setting up an appropriate construction location; S2, marking an extension path, construction starting point and construction end point of a gateway; S3, constructing first cast-in-place piles; S4, connecting and fixing the first cast-in-place piles on two sides by means of positioning frames; S5, excavating a first excavation pit and a second excavation pit, and providing second excavation pits on two sides of the gateway in the extension direction; S6, simultaneously constructing a third excavation pit, wherein the first excavation pit, the second excavation pit and the third excavation pit are arranged in a stepped shape; S7, continuing to excavate; S8, repeating S3-S6 until a second foundation pit body is formed; S9, completing the construction of third cast-in-place piles; S10, forming a first communicating foundation pit; S11, repeating S3-S10 until a second communicating foundation pit and continuous cast-in-place piles in rows are completed; and S12, erecting formwork and performing pouring and filling, and thereby forming a designed target pit. The present invention makes construction efficient, can greatly improve the overall construction efficiency, and can also ensure the operation safety.
Est prévu dans la présente invention un procédé de construction pour construire une passerelle dans un espace limité sous un pont. Le procédé de construction comprend les étapes suivantes consistant à : S1, définir un emplacement de construction approprié ; S2, marquer un trajet d'extension, un point de début de construction et un point de fin de construction d'une passerelle ; S3, construire des premiers pieux coulés sur place ; S4, relier et fixer les premiers pieux coulés sur place sur deux côtés au moyen de cadres de positionnement ; S5, excaver une première fosse d'excavation et une deuxième fosse d'excavation, et fournir des deuxièmes fosses d'excavation sur deux côtés de la passerelle dans la direction d'extension ; S6, construire simultanément une troisième fosse d'excavation, la première fosse d'excavation, la deuxième fosse d'excavation et la troisième fosse d'excavation étant agencées selon une forme étagée ; S7, continuer à excaver ; S8, répéter S3-S6 jusqu'à ce qu'un second corps de fosse de fondation soit formé ; S9, terminer la construction de troisièmes pieux coulés sur place ; S10, former une première fosse de fondation communicante ; S11, répéter S3-S10 jusqu'à ce qu'une seconde fosse de fondation communicante et des pieux coulés sur place continus en rangées soient terminés ; et S12, ériger le coffrage et effectuer un coulage et un remplissage, et former ainsi une fosse cible désignée. La présente invention rend la construction efficace, permet d'améliorer considérablement l'efficacité globale de la construction et également d'assurer la sécurité de fonctionnement.
本发明提供一种下穿桥梁的有限空间内施工闸道的施工方法,包括以下步骤:S1、设置合适的施工位置;S2、标记出闸道的走线路径、施工起点和终点;S3、进行第一灌注桩的施工;S4、两侧的第一灌注桩通过定位架连接固定;S5、开挖第一开挖坑和第二开挖坑,同时在沿闸道的走向两侧设置第二开挖坑;S6、同时进行第三开挖坑的施工,第一开挖坑、第二开挖坑和第三开挖坑成阶梯设置;S7、继续开挖;S8、循环S3~S6,直至形成第二基坑体;S9、完成第三灌注桩的施工;S10、形成第一连通基坑;S11、重复S3~S10,直至完成第二连通基坑和连排灌注桩;S12、立模浇筑填充,形成设计目标坑。本发明施工高效,能大幅度提高整体的施工效率,保证作业安全。
CONSTRUCTION METHOD FOR CONSTRUCTING GATEWAY IN LIMITED SPACE UNDERNEATH BRIDGE
PROCÉDÉ DE CONSTRUCTION POUR CONSTRUIRE UNE PASSERELLE DANS UN ESPACE LIMITÉ SOUS UN PONT
下穿桥梁的有限空间内施工闸道的施工方法
HUANG WEI (Autor:in) / WANG ZHIMIN (Autor:in) / LIU WEN (Autor:in) / YANG RUI (Autor:in) / JIANG HUADONG (Autor:in) / ZHANG LIXIANG (Autor:in) / XU ZHUO (Autor:in) / YANG TAO (Autor:in) / ZHAO ZICHEN (Autor:in) / MA JINCHUAN (Autor:in)
12.12.2024
Patent
Elektronische Ressource
Chinesisch
Construction method for constructing gateway in limited space of underneath pass bridge
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2024
|Construction method for underneath pass of high-speed bridge
Europäisches Patentamt | 2022
|Construction method for tunnel underneath passing through existing bridge pile foundation
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|