Steel tube superposed column and construction method for core concrete pouring of the steel tube superposed column
The invention discloses a steel tube superposed column and a construction method for core concrete pouring of the steel tube superposed column. The construction method comprises the steps: forming a pouring and tamping hole matching with a pump pipe on the side wall of a steel tube column, wherein the pouring and tamping hole is above an upper-storey floor slab; installing the steel tube column and mounting the upper-storey floor slab, inserting the pump pipe into the pouring and tamping hole on the upper-storey floor slab, and pumping concrete to pour the core of a lower-storey steel pipe column. The invention further discloses the steel tube superposed column. Workers can work on the floor slab; the risks of working at elevated heights and overhead hoisting a hopper at night by an overhead tower crane can be avoided at the source; the influence of strong wind weather on the engineering construction progress is reduced and the construction progress is accelerated; after the pouring and tamping hole is formed, the core concrete of the steel tube column and the concrete of wall columns and floor slabs are poured synchronously on the same floor. It is unnecessary to utilize high-cast and non-vibration concrete as the column core concrete, so that the construction quality is ensured and the cost is reduced.
Steel tube superposed column and construction method for core concrete pouring of the steel tube superposed column
The invention discloses a steel tube superposed column and a construction method for core concrete pouring of the steel tube superposed column. The construction method comprises the steps: forming a pouring and tamping hole matching with a pump pipe on the side wall of a steel tube column, wherein the pouring and tamping hole is above an upper-storey floor slab; installing the steel tube column and mounting the upper-storey floor slab, inserting the pump pipe into the pouring and tamping hole on the upper-storey floor slab, and pumping concrete to pour the core of a lower-storey steel pipe column. The invention further discloses the steel tube superposed column. Workers can work on the floor slab; the risks of working at elevated heights and overhead hoisting a hopper at night by an overhead tower crane can be avoided at the source; the influence of strong wind weather on the engineering construction progress is reduced and the construction progress is accelerated; after the pouring and tamping hole is formed, the core concrete of the steel tube column and the concrete of wall columns and floor slabs are poured synchronously on the same floor. It is unnecessary to utilize high-cast and non-vibration concrete as the column core concrete, so that the construction quality is ensured and the cost is reduced.
Steel tube superposed column and construction method for core concrete pouring of the steel tube superposed column
QIN XIAOFENG (author) / WANG LEI (author) / LI PING (author) / WU LIFENG (author) / HUANG JINGXIN (author) / WANG YUKAI (author) / JIANG YONGJIA (author) / LONG LINGFEI (author) / CHEN XIAODONG (author)
2015-04-29
Patent
Electronic Resource
English
Construction method of steel pipe concrete superposed column
European Patent Office | 2020
|Concrete-filled steel tube truss prestress superposed beam
European Patent Office | 2021
|European Patent Office | 2020
|European Patent Office | 2024
|Concrete pouring monitoring method for steel tube-concrete laminated column