A platform for research: civil engineering, architecture and urbanism
Waterproofing method of deformation joint of underground pipe galleries
The invention provides a waterproofing method of a deformation joint of underground pipe galleries. The method includes the steps that a rubber water stop strip is mounted at the position of a gap between the two pipe galleries, and the center of the rubber water stop strip needs to coincide with the center line of the deformation joint. The rubber water stop strip needs to be subjected to trial assembly in advance on an overlapping portion before being mounted, the overlapped position is determined through line drawing, it needs to be guaranteed that the position about 1 cm for being filled with sheet rubber is reserved in the middle during line drawing, rubber at one end of the rubber water stop strip with a steel edge is cut in by about 30 cm with a cutting machine, and the rubber portions at the two overlapped ends of the rubber water stop strip are ground through an angle grinder. According to the waterproofing method of the deformation joint of the underground pipe galleries, thegap of the pipe galleries can be subjected to sealing waterproofing.
地下管廊变形缝防水方法,包括:在两个管廊之间的缝隙处安装橡胶止水带,并且橡胶止水带的中心应与变形缝中心线相重合。橡胶止水带安装前要在搭接部分提前试拼,并画线确定要搭接位置,画线时必需保证中间留有1cm左右填塞生胶片的位置,用切割机将带有钢边的橡胶止水带一头的橡胶切进去30cm左右,并用角磨机将橡胶止水带要搭接两头橡胶部分磨平。本发明提供的地下管廊变形缝防水方法,能够管廊的缝隙进行密封防水。
Waterproofing method of deformation joint of underground pipe galleries
The invention provides a waterproofing method of a deformation joint of underground pipe galleries. The method includes the steps that a rubber water stop strip is mounted at the position of a gap between the two pipe galleries, and the center of the rubber water stop strip needs to coincide with the center line of the deformation joint. The rubber water stop strip needs to be subjected to trial assembly in advance on an overlapping portion before being mounted, the overlapped position is determined through line drawing, it needs to be guaranteed that the position about 1 cm for being filled with sheet rubber is reserved in the middle during line drawing, rubber at one end of the rubber water stop strip with a steel edge is cut in by about 30 cm with a cutting machine, and the rubber portions at the two overlapped ends of the rubber water stop strip are ground through an angle grinder. According to the waterproofing method of the deformation joint of the underground pipe galleries, thegap of the pipe galleries can be subjected to sealing waterproofing.
地下管廊变形缝防水方法,包括:在两个管廊之间的缝隙处安装橡胶止水带,并且橡胶止水带的中心应与变形缝中心线相重合。橡胶止水带安装前要在搭接部分提前试拼,并画线确定要搭接位置,画线时必需保证中间留有1cm左右填塞生胶片的位置,用切割机将带有钢边的橡胶止水带一头的橡胶切进去30cm左右,并用角磨机将橡胶止水带要搭接两头橡胶部分磨平。本发明提供的地下管廊变形缝防水方法,能够管廊的缝隙进行密封防水。
Waterproofing method of deformation joint of underground pipe galleries
地下管廊变形缝防水方法
GAO YANG (author) / REN YILIANG (author) / LI XING (author) / YU TIANREN (author) / ZHUANG HONGWEI (author) / HE XIAOLONG (author) / YUAN RUIJUN (author) / BAI YONGJIE (author) / LIU CHUNLEI (author) / LI HAO (author)
2020-04-24
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Cooling of underground galleries
Engineering Index Backfile | 1959
|High-viscosity epoxy resins for waterproofing and reinforcement of galleries
British Library Conference Proceedings | 2018
|Cooling of underground galleries
Engineering Index Backfile | 1959
|Sealed underground? Waterproofing
Tema Archive | 2003
|