Construction method for treating soft soil foundation of hydraulic reclamation project
The invention relates to a construction method for treating a soft soil foundation of a hydraulic reclamation project. The construction method comprises the following steps of (1) site elevation measurement and paying-off, (2) excavation of a temporary drainage ditch, (3) disturbance and rolling compaction, (4) site airing and drainage, (5) establishment of a drainage system, (6) arrangement of light well points, (7) precipitation, (8) earthwork outward turning and transferring, (9) secondary precipitation through combination of the light well points and a tube well, (10) dynamic compaction, and (11) bearing capacity detection, wherein in the step (3), a backhoe type land and water excavator is adopted to backhoe and be inserted into a soil layer by a certain depth and then shake to applyvibration, and then a land and water excavator or a bulldozer is adopted to roll a construction area in a segmented mode. By means of the construction method, the treatment capacity of the soft soil foundation is improved, the water content of the soft soil foundation is rapidly and effectively reduced, the bearing capacity of the soft soil foundation is improved, and smooth proceeding of subsequent construction is guaranteed.
本发明涉及一种对吹填工程软土地基进行处理的施工方法。包括以下步骤,(1)场地标高测量和放线的步骤;(2)开挖临时排水沟的步骤;(3)扰动和碾压的步骤,采用反铲式水陆挖掘机反铲插入土层内一定深度后晃动施振,之后采用水陆挖掘机或推土机分段对施工区进行碾压;(4)场地晾晒和排水的步骤;(5)建立排水系统的步骤;(6)布设轻型井点的步骤;(7)降水的步骤;(8)土方外翻、倒运的步骤;(9)轻型井点联合管井进行二次降水的步骤;(10)强夯的步骤;(11)承载力检测的步骤。本发明的施工方法提升了对软土地基的处理能力,快速有效地降低了软土地基的含水率且提升了软土地基的承载力,保障了后续施工的顺利进行。
Construction method for treating soft soil foundation of hydraulic reclamation project
The invention relates to a construction method for treating a soft soil foundation of a hydraulic reclamation project. The construction method comprises the following steps of (1) site elevation measurement and paying-off, (2) excavation of a temporary drainage ditch, (3) disturbance and rolling compaction, (4) site airing and drainage, (5) establishment of a drainage system, (6) arrangement of light well points, (7) precipitation, (8) earthwork outward turning and transferring, (9) secondary precipitation through combination of the light well points and a tube well, (10) dynamic compaction, and (11) bearing capacity detection, wherein in the step (3), a backhoe type land and water excavator is adopted to backhoe and be inserted into a soil layer by a certain depth and then shake to applyvibration, and then a land and water excavator or a bulldozer is adopted to roll a construction area in a segmented mode. By means of the construction method, the treatment capacity of the soft soil foundation is improved, the water content of the soft soil foundation is rapidly and effectively reduced, the bearing capacity of the soft soil foundation is improved, and smooth proceeding of subsequent construction is guaranteed.
本发明涉及一种对吹填工程软土地基进行处理的施工方法。包括以下步骤,(1)场地标高测量和放线的步骤;(2)开挖临时排水沟的步骤;(3)扰动和碾压的步骤,采用反铲式水陆挖掘机反铲插入土层内一定深度后晃动施振,之后采用水陆挖掘机或推土机分段对施工区进行碾压;(4)场地晾晒和排水的步骤;(5)建立排水系统的步骤;(6)布设轻型井点的步骤;(7)降水的步骤;(8)土方外翻、倒运的步骤;(9)轻型井点联合管井进行二次降水的步骤;(10)强夯的步骤;(11)承载力检测的步骤。本发明的施工方法提升了对软土地基的处理能力,快速有效地降低了软土地基的含水率且提升了软土地基的承载力,保障了后续施工的顺利进行。
Construction method for treating soft soil foundation of hydraulic reclamation project
一种对吹填工程软土地基进行处理的施工方法
WANG XU (author) / WU TUO (author) / FAN LEI (author) / HUANG LIANG (author) / WANG YUCHEN (author) / PANG XIAOFENG (author) / QIU XIAOWEI (author)
2020-12-04
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2015
|Gravity flow method hydraulic reclamation type foundation treatment construction process
European Patent Office | 2021
|European Patent Office | 2020
|Construction method of soft soil foundation pile foundation
European Patent Office | 2021
|European Patent Office | 2023
|