Construction method for reinforcing complex stratum through grouting steel pipe piles
The invention relates to the technical field of constructional engineering, in particular to a construction method for reinforcing a complex stratum through grouting steel pipe piles. The constructionmethod comprises the following steps of (1) tamping a site, ensuring that the site is flat, and performing measuring and positioning; (2) using a drilling machine for drilling at the positioned position to form pile holes; (3) inserting grouting pipes into the bottoms of the pile holes and injecting slurry by adopting a hole bottom slurry return method until pure slurry emerges from hole openingsof the pile holes, and then stopping grouting; and (4) installing steel pipes at the positions of the pile holes. The construction method has the advantages of short curing time and excellent mechanical properties.
本发明涉及建筑工程技术领域,具体涉及一种利用注浆钢管桩加固复杂地层的施工方法,所述方法包括如下步骤:(1)夯实场地,保证场地平整,进行测量定位;(2)在定位的位置采用钻孔机钻孔,形成桩孔;(3)采用孔底返浆法,将注浆管插至桩孔孔底并注入浆料,直至纯净的浆料从桩孔孔口冒出,终止注浆;(4)在桩孔位置安装钢管。本发明具有固化时间短、力学性能优异的优点。
Construction method for reinforcing complex stratum through grouting steel pipe piles
The invention relates to the technical field of constructional engineering, in particular to a construction method for reinforcing a complex stratum through grouting steel pipe piles. The constructionmethod comprises the following steps of (1) tamping a site, ensuring that the site is flat, and performing measuring and positioning; (2) using a drilling machine for drilling at the positioned position to form pile holes; (3) inserting grouting pipes into the bottoms of the pile holes and injecting slurry by adopting a hole bottom slurry return method until pure slurry emerges from hole openingsof the pile holes, and then stopping grouting; and (4) installing steel pipes at the positions of the pile holes. The construction method has the advantages of short curing time and excellent mechanical properties.
本发明涉及建筑工程技术领域,具体涉及一种利用注浆钢管桩加固复杂地层的施工方法,所述方法包括如下步骤:(1)夯实场地,保证场地平整,进行测量定位;(2)在定位的位置采用钻孔机钻孔,形成桩孔;(3)采用孔底返浆法,将注浆管插至桩孔孔底并注入浆料,直至纯净的浆料从桩孔孔口冒出,终止注浆;(4)在桩孔位置安装钢管。本发明具有固化时间短、力学性能优异的优点。
Construction method for reinforcing complex stratum through grouting steel pipe piles
利用注浆钢管桩加固复杂地层的施工方法
GUO JIANGONG (author) / CHEN XIAOHUI (author) / YANG JUNFENG (author) / XIAO FANGTENG (author) / YANG ZHIYONG (author)
2020-12-08
Patent
Electronic Resource
Chinese
European Patent Office | 2016
|Method for reinforcing deep backfill foundation through deep grouting and steel pipe piles
European Patent Office | 2023
|Method for reinforcing house foundation based on grouting steel pipe piles
European Patent Office | 2024
|Film bag grouting device for reinforcing specific area of stratum and grouting reinforcing method
European Patent Office | 2021
|Grouting pipe for miscellaneous fill stratum and construction method
European Patent Office | 2015
|