Brick well construction method
The invention relates to a brick well construction method. The brick well construction method comprises the following steps that S1, a well bottom plate is designed and prefabricated; S2, a well pit is designed and excavated according to the size of the well bottom plate; S3, the well bottom plate is hoisted and fixed in the to-be-installed well pit; and S4, a well body is built on the well bottomplate. According to the brick well construction method, during construction, after the well pit is excavated, the prefabricated well bottom plate can be directly hoisted and fixed in the to-be-installed well pit, then the well body can be built on the well bottom plate on the same day, waiting for solidification of the well bottom plate is not needed, thus the construction time is shortened, theconstruction efficiency is improved, the time of existence of the well pit is shortened, then the probability of accidents is decreased, and the construction safety is improved.
本申请涉及一种砖砌井施工方法,包括以下步骤,S1,设计并预制井底板;S2,根据井底板大小设计并开挖井坑;S3,将所述井底板吊装固定于待安装的井坑内;S4,在所述井底板上砌筑井体。本申请的砖砌井施工方法在施工时,开挖井坑之后可以直接将预制完成的井底板吊装固定于待安装的井坑内,然后当天就可以在井底板上砌筑井体,无需等待井底板固化,从而缩短施工时间,提高施工效率,减少井坑存在的时间,进而减小意外发生的概率,提高了施工的安全性。
Brick well construction method
The invention relates to a brick well construction method. The brick well construction method comprises the following steps that S1, a well bottom plate is designed and prefabricated; S2, a well pit is designed and excavated according to the size of the well bottom plate; S3, the well bottom plate is hoisted and fixed in the to-be-installed well pit; and S4, a well body is built on the well bottomplate. According to the brick well construction method, during construction, after the well pit is excavated, the prefabricated well bottom plate can be directly hoisted and fixed in the to-be-installed well pit, then the well body can be built on the well bottom plate on the same day, waiting for solidification of the well bottom plate is not needed, thus the construction time is shortened, theconstruction efficiency is improved, the time of existence of the well pit is shortened, then the probability of accidents is decreased, and the construction safety is improved.
本申请涉及一种砖砌井施工方法,包括以下步骤,S1,设计并预制井底板;S2,根据井底板大小设计并开挖井坑;S3,将所述井底板吊装固定于待安装的井坑内;S4,在所述井底板上砌筑井体。本申请的砖砌井施工方法在施工时,开挖井坑之后可以直接将预制完成的井底板吊装固定于待安装的井坑内,然后当天就可以在井底板上砌筑井体,无需等待井底板固化,从而缩短施工时间,提高施工效率,减少井坑存在的时间,进而减小意外发生的概率,提高了施工的安全性。
Brick well construction method
一种砖砌井施工方法
LI BIN (author) / WANG ZHIXIN (author) / LU YONGDA (author)
2020-12-11
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of anti-seepage brick inspection well
European Patent Office | 2021
|Construction method of concrete module brick inspection well
European Patent Office | 2022
|Prefabricated well wall brick structure for well and construction method thereof
European Patent Office | 2021
|METHOD CONSTRUCTION CLAY BRICK AND STRUCTURE CLAY BRICK EASY CONSTRUCTION
European Patent Office | 2017
|METHOD CONSTRUCTION CLAY BRICK AND STRUCTURE CLAY BRICK EASY CONSTRUCTION
European Patent Office | 2017