Arid region roadbed filler construction method
The invention provides an arid region roadbed filler construction method, and relates to the technical field of foundation construction. The arid region roadbed filler construction method comprises the following steps: S1, construction measurement; S2, original ground surface cleaning: turf and plant root systems in the roadbed range should be removed, and the turf and the plant root systems are removed to the required thickness according to design; S3, material covering in a material field: determining the water consumption for roadbed filler material covering, and then performing material covering in the material covering field; S4, earth is excavated and transported, specifically, earth materials in an earth material yard are excavated and transported to a construction site through a dumper; and S5, layered paving is conducted, specifically, gridding distribution is conducted on the soil filling section, lattices are drawn through lime, then the soil is stacked in the drawn area, the filler is paved through a bulldozer, and fine flattening and layered flattening are conducted through a land leveler. According to the filler construction method, a large amount of time and cost aresaved for nearby material taking and nearby construction, precise control is achieved during construction, and it is guaranteed that the roadbed has excellent strength and service life.
本发明提供一种干旱地区路基填料施工方法,涉及地基施工技术领域。该干旱地区路基填料施工方法,包括以下步骤:S1施工测量;S2.原地表清理,在路基范围内的草皮及植物根系应清除,并按照设计清除至要求厚度;S3.料场闷料,确定路基填料闷料用水量,然后在闷料场进行闷料;S4.挖运土方,挖取土料场的土料,然后使用自卸车运送至施工点;S5.分层摊铺,填土区段按照网格化布料,并用白灰画出框格,然后将土料堆放到画好的区域,填料用推土机摊铺,平地机精平,分层摊平。本发明设计的填料施工方法就近取料就近施工节约了大量时间和成本,而且施工时精确控制,保证了路基具有极好的强度和使用寿命。
Arid region roadbed filler construction method
The invention provides an arid region roadbed filler construction method, and relates to the technical field of foundation construction. The arid region roadbed filler construction method comprises the following steps: S1, construction measurement; S2, original ground surface cleaning: turf and plant root systems in the roadbed range should be removed, and the turf and the plant root systems are removed to the required thickness according to design; S3, material covering in a material field: determining the water consumption for roadbed filler material covering, and then performing material covering in the material covering field; S4, earth is excavated and transported, specifically, earth materials in an earth material yard are excavated and transported to a construction site through a dumper; and S5, layered paving is conducted, specifically, gridding distribution is conducted on the soil filling section, lattices are drawn through lime, then the soil is stacked in the drawn area, the filler is paved through a bulldozer, and fine flattening and layered flattening are conducted through a land leveler. According to the filler construction method, a large amount of time and cost aresaved for nearby material taking and nearby construction, precise control is achieved during construction, and it is guaranteed that the roadbed has excellent strength and service life.
本发明提供一种干旱地区路基填料施工方法,涉及地基施工技术领域。该干旱地区路基填料施工方法,包括以下步骤:S1施工测量;S2.原地表清理,在路基范围内的草皮及植物根系应清除,并按照设计清除至要求厚度;S3.料场闷料,确定路基填料闷料用水量,然后在闷料场进行闷料;S4.挖运土方,挖取土料场的土料,然后使用自卸车运送至施工点;S5.分层摊铺,填土区段按照网格化布料,并用白灰画出框格,然后将土料堆放到画好的区域,填料用推土机摊铺,平地机精平,分层摊平。本发明设计的填料施工方法就近取料就近施工节约了大量时间和成本,而且施工时精确控制,保证了路基具有极好的强度和使用寿命。
Arid region roadbed filler construction method
一种干旱地区路基填料施工方法
AI ZHENXI (author) / WANG ZHIGANG (author) / SHEN YANSHUANG (author) / ZHANG XIAOBO (author) / LI HAILONG (author) / DENG PING (author) / FENG SHENGWU (author) / DING PEIYUN (author) / DING YANBO (author)
2021-04-02
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
European Patent Office | 2024
|Recycled roadbed base layer filler and recycled roadbed construction method
European Patent Office | 2021
|Bauxite mill tailing composite roadbed filler and roadbed construction method thereof
European Patent Office | 2022
|Carbonaceous shale filler roadbed filling construction method
European Patent Office | 2023
|