Outer wall post-cast strip waterproof construction method
The invention discloses an outer wall post-cast strip waterproof construction method. The outer wall post-cast strip waterproof construction method comprises the steps that firstly, a post-cast strip is reserved during construction of a reinforced concrete structure outer wall of a basement, and an extending part is reserved on the outer side of the post-cast strip and extends out of the outer side face of the reinforced concrete structure outer wall; and then a water stop steel plate is arranged at the joint of the reinforced concrete structure outer wall and the post-cast strip, the post-cast strip and the extension part are poured together, and then outer wall anti-seepage construction is carried out. According to the outer wall post-cast strip waterproof construction method, the leakage risk at the basement exterior wall construction joint is greatly reduced; and construction is relatively easy and convenient, manpower and material resources are saved, a post-cast strip outer wall formwork does not need to be erected again after backfilling is completed, the construction speed is increased, and the construction cost is saved.
本发明公开了一种外墙后浇带防水的施工方法,首先在地下室的钢筋混凝土结构外墙施工时留设后浇带,并在后浇带的外侧预留延伸部,使延伸部从钢筋混凝土结构外墙的外侧面伸出,然后在钢筋混凝土结构外墙与后浇带的交接处置入止水钢板,浇筑后浇带时连同延伸部一起浇筑,随后进行外墙防渗漏施工。本发明的施工方法大大降低了地下室外墙施工缝处的渗漏风险;而且施工较为简便,节省人力物力,回填完成后不需要重新支设后浇带外墙模板,加快了施工速度,节省了施工成本。
Outer wall post-cast strip waterproof construction method
The invention discloses an outer wall post-cast strip waterproof construction method. The outer wall post-cast strip waterproof construction method comprises the steps that firstly, a post-cast strip is reserved during construction of a reinforced concrete structure outer wall of a basement, and an extending part is reserved on the outer side of the post-cast strip and extends out of the outer side face of the reinforced concrete structure outer wall; and then a water stop steel plate is arranged at the joint of the reinforced concrete structure outer wall and the post-cast strip, the post-cast strip and the extension part are poured together, and then outer wall anti-seepage construction is carried out. According to the outer wall post-cast strip waterproof construction method, the leakage risk at the basement exterior wall construction joint is greatly reduced; and construction is relatively easy and convenient, manpower and material resources are saved, a post-cast strip outer wall formwork does not need to be erected again after backfilling is completed, the construction speed is increased, and the construction cost is saved.
本发明公开了一种外墙后浇带防水的施工方法,首先在地下室的钢筋混凝土结构外墙施工时留设后浇带,并在后浇带的外侧预留延伸部,使延伸部从钢筋混凝土结构外墙的外侧面伸出,然后在钢筋混凝土结构外墙与后浇带的交接处置入止水钢板,浇筑后浇带时连同延伸部一起浇筑,随后进行外墙防渗漏施工。本发明的施工方法大大降低了地下室外墙施工缝处的渗漏风险;而且施工较为简便,节省人力物力,回填完成后不需要重新支设后浇带外墙模板,加快了施工速度,节省了施工成本。
Outer wall post-cast strip waterproof construction method
一种外墙后浇带防水的施工方法
CAI WANCHANG (author) / ZHAO WENDI (author) / LIN JINPING (author) / LIU BANG (author) / YANG CHANG (author) / ZUO HONGWEI (author)
2021-04-09
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Waterproof construction method for side wall post-cast strip
European Patent Office | 2024
|Post-closed outer wall post-cast strip reinforcement construction method
European Patent Office | 2020
|Waterproof construction method for post-cast strip of basement wall
European Patent Office | 2024
|Construction method for basement outer wall post-cast strip
European Patent Office | 2023
|