Construction method for upper structure of steam turbine base
The invention discloses a construction method for an upper structure of a steam turbine base. The method comprises the following steps of S01, measuring, positioning and paying off; S02, scaffold engineering; S03, steel bar engineering; S04, formwork engineering; S05, embedded part engineering; S06, foundation bolt sleeve installing and fixing; S07, temperature measuring point arranging; S08, concrete engineering; S09, semi-finished product protecting; S10, deformation and settlement observing; and S11, secondary grouting. The problems that in the prior art, the supporting load of a scaffold is insufficient, and meanwhile the overall stability is poor are solved.
本发明公开了一种汽机基座上部结构施工方法,所述方法包括以下步骤:S01、测量定位放线;S02、脚手架工程;S03、钢筋工程;S04、模板工程;S05、预埋件工程;S06、地脚螺栓套管安装和固定;S07、测温点的布设;S08、混凝土工程;S09、半成品保护;S10、变形及沉降观测;S11、二次灌浆。以解决现有技术脚手架支撑载荷不足,同时整体稳定性较差的问题。
Construction method for upper structure of steam turbine base
The invention discloses a construction method for an upper structure of a steam turbine base. The method comprises the following steps of S01, measuring, positioning and paying off; S02, scaffold engineering; S03, steel bar engineering; S04, formwork engineering; S05, embedded part engineering; S06, foundation bolt sleeve installing and fixing; S07, temperature measuring point arranging; S08, concrete engineering; S09, semi-finished product protecting; S10, deformation and settlement observing; and S11, secondary grouting. The problems that in the prior art, the supporting load of a scaffold is insufficient, and meanwhile the overall stability is poor are solved.
本发明公开了一种汽机基座上部结构施工方法,所述方法包括以下步骤:S01、测量定位放线;S02、脚手架工程;S03、钢筋工程;S04、模板工程;S05、预埋件工程;S06、地脚螺栓套管安装和固定;S07、测温点的布设;S08、混凝土工程;S09、半成品保护;S10、变形及沉降观测;S11、二次灌浆。以解决现有技术脚手架支撑载荷不足,同时整体稳定性较差的问题。
Construction method for upper structure of steam turbine base
一种汽机基座上部结构施工方法
XIAO XIANGHUI (author) / BAI SHUJUAN (author) / LI CHAO (author) / DENG JIAN (author) / ZHANG YUZHU (author) / CHEN HUAFENG (author) / LUO JIE (author)
2021-08-17
Patent
Electronic Resource
Chinese
Construction method for pre-embedding bolt sleeve on upper structure of steam turbine generator base
European Patent Office | 2021
|European Patent Office | 2024
|Construction method for pre-embedded casing pipe of steam turbine generator unit base
European Patent Office | 2024
|Steam turbine foundation secondary grouting permanent formwork structure and construction method
European Patent Office | 2024
|Present problems in steam turbine construction
Engineering Index Backfile | 1936
|