The invention relates to an installation construction method of an external wall insulation board. The external wall insulation board comprises a bottom plate, a supporting table, an ash removal device and a coating device. The installation construction method can solve the following problems that in the process of coating bonding slurry on an existing external wall insulation board, a, the bonding slurry is manually coated on the coating surface of the external wall insulation board, the phenomenon of uneven or incomplete coating is prone to occurring in the mode, so that the phenomenon of incomplete bonding or falling off is prone to occurring in the installation process of the external wall insulation board, and the construction quality is reduced; and b, in the storage process of the external wall insulation board, a large amount of dust is extremely prone to adhering to the surface of the external wall insulation board, if the dust is not removed, the adhesion of the bonding slurry is reduced, a traditional removal mode is manual removal, time and labor are consumed, the cleaning effect is poor, so that the coating efficiency of the external wall insulation board is low, and then the installation construction progress of the external wall insulation board is influenced.
本发明涉及一种外墙保温板安装施工方法,包括底板、支撑台、清灰装置和涂料装置。本发明可以解决现有的外墙保温板在涂抹粘接浆料的过程中可能会遇到以下难题:a.通过人工手动对外墙保温板的涂料面进行粘接浆料的涂抹,该种方式容易出现涂抹不均或不完全的现象,使得外墙保温板在安装过程中容易出现粘接不完全或脱落的现象,从而降低了施工质量;b.外墙保温板在存放过程中,其表面极易粘附大量灰尘,如不进行清除,则会降低粘接浆料的粘附性,传统的清除方式是人工手动清除,不仅耗时耗力,且清洁效果较差,导致外墙保温板的涂料效率较低,进而影响了其安装施工进度。
Installation construction method of external wall insulation board
The invention relates to an installation construction method of an external wall insulation board. The external wall insulation board comprises a bottom plate, a supporting table, an ash removal device and a coating device. The installation construction method can solve the following problems that in the process of coating bonding slurry on an existing external wall insulation board, a, the bonding slurry is manually coated on the coating surface of the external wall insulation board, the phenomenon of uneven or incomplete coating is prone to occurring in the mode, so that the phenomenon of incomplete bonding or falling off is prone to occurring in the installation process of the external wall insulation board, and the construction quality is reduced; and b, in the storage process of the external wall insulation board, a large amount of dust is extremely prone to adhering to the surface of the external wall insulation board, if the dust is not removed, the adhesion of the bonding slurry is reduced, a traditional removal mode is manual removal, time and labor are consumed, the cleaning effect is poor, so that the coating efficiency of the external wall insulation board is low, and then the installation construction progress of the external wall insulation board is influenced.
本发明涉及一种外墙保温板安装施工方法,包括底板、支撑台、清灰装置和涂料装置。本发明可以解决现有的外墙保温板在涂抹粘接浆料的过程中可能会遇到以下难题:a.通过人工手动对外墙保温板的涂料面进行粘接浆料的涂抹,该种方式容易出现涂抹不均或不完全的现象,使得外墙保温板在安装过程中容易出现粘接不完全或脱落的现象,从而降低了施工质量;b.外墙保温板在存放过程中,其表面极易粘附大量灰尘,如不进行清除,则会降低粘接浆料的粘附性,传统的清除方式是人工手动清除,不仅耗时耗力,且清洁效果较差,导致外墙保温板的涂料效率较低,进而影响了其安装施工进度。
Installation construction method of external wall insulation board
一种外墙保温板安装施工方法
SHU XIONGWU (author)
2021-09-03
Patent
Electronic Resource
Chinese
Building external wall insulation board installation construction method
European Patent Office | 2021
|Installation and construction process of external wall insulation board
European Patent Office | 2023
|Installation method of external wall heat insulation integrated board
European Patent Office | 2024
|Installation method of external wall heat insulation integrated board
European Patent Office | 2023
|Building external wall insulation board construction method
European Patent Office | 2022
|