Concrete prefabricated stair and installation and construction method thereof
The invention relates to a concrete prefabricated stair which comprises an upper connecting end connected with an upper platform and a lower connecting end connected with a lower platform, the prefabricated stair is composed of a first module and a second module, the first module is arranged on the side close to a wall, and the second module is arranged on the side close to a guardrail; the first module and the second module are respectively provided with respective pin reserved holes and hoisting embedded parts; the installation construction method of the concrete prefabricated stair comprises the following steps: 1) calculating the weight of the components, and performing overall calculation of the prefabricated stair according to a designed construction drawing; (2)determining the optimal hoisting weight of a tower crane used in the whole project in combination with a construction total package unit, and splitting the prefabricated staircase into a plurality of blocks according to the hoisting weight; (3) molds are manufactured in a factory for production, and all the produced concrete block components are transported to a site; 4) respectively mounting and fixing each block on the upper platform and the lower platform on site; and (5) if the stair joints among the blocks are larger than 50 mm, using mortar for blocking.
本发明涉及一种混凝土预制楼梯,包括与上平台连接的上连接端,与下平台连接的下连接端,该预制楼梯由第一组块和第二组块组成,第一组块设置于靠墙一侧,第二组块设置于靠扶栏一侧;第一组块、第二组块分别设有各自的销件预留洞和吊装埋件;上述混凝土预制楼梯的安装施工方法,1)计算构件重量,根据设计的施工图纸先进行预制楼梯的整体计算;2)与施工总包单位结合确定整体工程使用的塔吊最佳吊重,根据吊重将预制楼梯拆分成多个组块;3)工厂制作模具进行生产,将生产好的各混凝土组块构件运输至现场;4)现场将各组块分别安装到上平台和下平台上并固定;5)各组块之间的楼梯接缝若大于50mm,则采用砂浆封堵。
Concrete prefabricated stair and installation and construction method thereof
The invention relates to a concrete prefabricated stair which comprises an upper connecting end connected with an upper platform and a lower connecting end connected with a lower platform, the prefabricated stair is composed of a first module and a second module, the first module is arranged on the side close to a wall, and the second module is arranged on the side close to a guardrail; the first module and the second module are respectively provided with respective pin reserved holes and hoisting embedded parts; the installation construction method of the concrete prefabricated stair comprises the following steps: 1) calculating the weight of the components, and performing overall calculation of the prefabricated stair according to a designed construction drawing; (2)determining the optimal hoisting weight of a tower crane used in the whole project in combination with a construction total package unit, and splitting the prefabricated staircase into a plurality of blocks according to the hoisting weight; (3) molds are manufactured in a factory for production, and all the produced concrete block components are transported to a site; 4) respectively mounting and fixing each block on the upper platform and the lower platform on site; and (5) if the stair joints among the blocks are larger than 50 mm, using mortar for blocking.
本发明涉及一种混凝土预制楼梯,包括与上平台连接的上连接端,与下平台连接的下连接端,该预制楼梯由第一组块和第二组块组成,第一组块设置于靠墙一侧,第二组块设置于靠扶栏一侧;第一组块、第二组块分别设有各自的销件预留洞和吊装埋件;上述混凝土预制楼梯的安装施工方法,1)计算构件重量,根据设计的施工图纸先进行预制楼梯的整体计算;2)与施工总包单位结合确定整体工程使用的塔吊最佳吊重,根据吊重将预制楼梯拆分成多个组块;3)工厂制作模具进行生产,将生产好的各混凝土组块构件运输至现场;4)现场将各组块分别安装到上平台和下平台上并固定;5)各组块之间的楼梯接缝若大于50mm,则采用砂浆封堵。
Concrete prefabricated stair and installation and construction method thereof
混凝土预制楼梯及其安装施工方法
SHEN HANBIN (author) / ZHANG LILIN (author) / ZHANG HUANLUAN (author)
2021-11-26
Patent
Electronic Resource
Chinese
Prefabricated building stair installation construction method
European Patent Office | 2020
|