Building pile foundation construction method
The invention relates to the technical field of building construction, in particular to a building pile foundation construction method. Comprising the following steps that S1, surveying and setting out are conducted, a foundation is leveled, and the position of a pile foundation is marked; s2, a mud pit is dug between the pile holes, and drainage grooves are dug around the pile holes; s3, lowering and mounting the pile casing; s4, slurry is poured into the pile hole; s5, the positions of coordinate points and the drilling sequence are determined, and a drilling operation rack used for supporting a drilling machine is laid on the construction plane of the building pile foundation; s6, drilling is conducted; s7, hole cleaning; s8, lowering a reinforcement cage; s9, after hoisting of the reinforcement cage is finished, concrete pouring is conducted; and S10, after initial setting of the concrete, the pile casing is pulled out of the pile hole, and a pile foundation is formed. The construction method is convenient to operate, high in construction speed, capable of saving materials and obvious in economic benefit, and construction efficiency is improved while pile foundation construction quality is guaranteed. The method is mainly applied to the aspect of building pile foundation construction.
本发明涉及建筑施工技术领域,更具体而言,涉及一种建筑桩基施工方法。包括以下步骤:S1、测量放线、平整地基,对桩基位置做好标记;S2、在桩孔之间挖设泥浆池,桩孔的四周挖引流槽;S3、下放安装护筒;S4、向桩孔内灌注泥浆;S5、确定坐标点位置以及钻孔顺序,在建筑桩基施工平面上铺设用于支撑钻机的钻孔作业台架;S6、钻孔;S7、清孔;S8、下放钢筋笼;S9、钢筋笼吊装结束之后进行混凝土灌注;S10、混凝土初凝之后将护筒从桩孔当中拔出,形成桩基。本发明操作方便、施工速度快、节约材料,经济效益明显,保证桩基施工质量的同时提高了施工效率。本发明主要应用于建筑桩基施工方面。
Building pile foundation construction method
The invention relates to the technical field of building construction, in particular to a building pile foundation construction method. Comprising the following steps that S1, surveying and setting out are conducted, a foundation is leveled, and the position of a pile foundation is marked; s2, a mud pit is dug between the pile holes, and drainage grooves are dug around the pile holes; s3, lowering and mounting the pile casing; s4, slurry is poured into the pile hole; s5, the positions of coordinate points and the drilling sequence are determined, and a drilling operation rack used for supporting a drilling machine is laid on the construction plane of the building pile foundation; s6, drilling is conducted; s7, hole cleaning; s8, lowering a reinforcement cage; s9, after hoisting of the reinforcement cage is finished, concrete pouring is conducted; and S10, after initial setting of the concrete, the pile casing is pulled out of the pile hole, and a pile foundation is formed. The construction method is convenient to operate, high in construction speed, capable of saving materials and obvious in economic benefit, and construction efficiency is improved while pile foundation construction quality is guaranteed. The method is mainly applied to the aspect of building pile foundation construction.
本发明涉及建筑施工技术领域,更具体而言,涉及一种建筑桩基施工方法。包括以下步骤:S1、测量放线、平整地基,对桩基位置做好标记;S2、在桩孔之间挖设泥浆池,桩孔的四周挖引流槽;S3、下放安装护筒;S4、向桩孔内灌注泥浆;S5、确定坐标点位置以及钻孔顺序,在建筑桩基施工平面上铺设用于支撑钻机的钻孔作业台架;S6、钻孔;S7、清孔;S8、下放钢筋笼;S9、钢筋笼吊装结束之后进行混凝土灌注;S10、混凝土初凝之后将护筒从桩孔当中拔出,形成桩基。本发明操作方便、施工速度快、节约材料,经济效益明显,保证桩基施工质量的同时提高了施工效率。本发明主要应用于建筑桩基施工方面。
Building pile foundation construction method
一种建筑桩基施工方法
CUI JIANJUN (author) / HAN RUILIN (author) / QIN HONGLEI (author) / WEI ZHI (author) / LIU YONGQING (author) / MU JINFENG (author)
2022-03-18
Patent
Electronic Resource
Chinese