Road station main body structure construction method
The invention is suitable for the technical field of station main body structure construction, and provides a road station main body structure construction method which comprises the following steps: S1, vertically layering a main body structure; s2, a support is installed in the layered main body structure; s3, supporting construction is conducted on the main body structure, earthwork around the main body structure is excavated to the position below the elevation of a laminate of the station main body structure, cushion layer construction is conducted, and waterproof construction is conducted on the enclosure structure at the position of the preset laminate; s4, main ridges are erected on the supports, and secondary ridges are erected according to the positions of the main ridges; s5, reinforcing treatment is conducted on the main ridges and the secondary ridges; s6, templates are installed on the main ridges and the secondary ridges, and the templates are measured, verified and adjusted; s7, steel bars are installed on the formwork; s8, concrete pouring is conducted in the formwork; and S9, after concrete pouring is conducted, when the strength of concrete meets the preset requirement, the formwork and the support are dismantled. The construction efficiency of the station main body structure can be improved, the cost is saved, the construction safety is high, and the application range is wide.
本发明适用于车站主体结构施工技术领域,提供了一种路站主体结构施工方法,方法包括步骤:S1、将主体结构进行竖向分层;S2、通过在分层的主体结构中进行支架安装;S3、对主体结构进行支护施工,并对其周围开挖土方至车站主体结构的层板标高以下并进行垫层施工,在预设层板位置的围护结构上进行防水施工;S4、通过在支架上搭设主楞,根据主楞位置搭设次楞;S5、对主楞和次楞进行加强处理;S6、在主楞和次楞上安装模板,并对模板进行测量校验及调整;S7、在模板上安装钢筋;S8、对模板内进行砼浇筑;S9、通过砼浇筑后,当砼的强度达到预设的要求时,将模板和支架拆除。本发明能够提高站主体结构的施工效率,节约成本,施工的安全性高,使用广泛。
Road station main body structure construction method
The invention is suitable for the technical field of station main body structure construction, and provides a road station main body structure construction method which comprises the following steps: S1, vertically layering a main body structure; s2, a support is installed in the layered main body structure; s3, supporting construction is conducted on the main body structure, earthwork around the main body structure is excavated to the position below the elevation of a laminate of the station main body structure, cushion layer construction is conducted, and waterproof construction is conducted on the enclosure structure at the position of the preset laminate; s4, main ridges are erected on the supports, and secondary ridges are erected according to the positions of the main ridges; s5, reinforcing treatment is conducted on the main ridges and the secondary ridges; s6, templates are installed on the main ridges and the secondary ridges, and the templates are measured, verified and adjusted; s7, steel bars are installed on the formwork; s8, concrete pouring is conducted in the formwork; and S9, after concrete pouring is conducted, when the strength of concrete meets the preset requirement, the formwork and the support are dismantled. The construction efficiency of the station main body structure can be improved, the cost is saved, the construction safety is high, and the application range is wide.
本发明适用于车站主体结构施工技术领域,提供了一种路站主体结构施工方法,方法包括步骤:S1、将主体结构进行竖向分层;S2、通过在分层的主体结构中进行支架安装;S3、对主体结构进行支护施工,并对其周围开挖土方至车站主体结构的层板标高以下并进行垫层施工,在预设层板位置的围护结构上进行防水施工;S4、通过在支架上搭设主楞,根据主楞位置搭设次楞;S5、对主楞和次楞进行加强处理;S6、在主楞和次楞上安装模板,并对模板进行测量校验及调整;S7、在模板上安装钢筋;S8、对模板内进行砼浇筑;S9、通过砼浇筑后,当砼的强度达到预设的要求时,将模板和支架拆除。本发明能够提高站主体结构的施工效率,节约成本,施工的安全性高,使用广泛。
Road station main body structure construction method
一种路站主体结构施工方法
WANG HONGSONG (author) / REN CHANGCHUN (author) / HE JINXING (author)
2022-05-10
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Subway station construction main body enclosure structure
European Patent Office | 2023
|Subway station and accessory main body structure interface construction method
European Patent Office | 2023
|Auxiliary enclosure structure of parallel station main body and construction method
European Patent Office | 2020
|High-speed rail station building main body steel structure construction method
European Patent Office | 2023
|