The invention relates to a steel trestle double-wall steel cofferdam transporting and rapid assembling and lowering construction method. The method comprises the steps that firstly, a steel trestle is erected; secondly, the wall body of the double-wall steel cofferdam is prefabricated and machined in a blocking mode; thirdly, the steel casing used in pile foundation construction is lengthened; 4, erecting and assembling a bracket on the steel casing by using profile steel at the height of the steel casing close to the water surface; fifthly, the steel cofferdam is transported to the site in a blocking mode through a steel trestle, and a bottom section cofferdam is assembled on the assembling support; sixthly, a lowering system is installed on the top of the steel casing; seventhly, the bottom section cofferdam is integrally lifted, and the assembling supports are dismantled; eighthly, the bottom section cofferdam is integrally lowered, and the bottom section cofferdam automatically floats on the water surface; ninthly, the wall body of the upper section cofferdam is hoisted in a blocking mode, and the upper section cofferdam is heightened on the bottom section cofferdam; and tenthly, water is injected into the cofferdam to sink to the designated elevation. The large-scale double-wall steel cofferdam assembling and lowering precision and convenience are improved, and the large-scale double-wall steel cofferdam assembling and lowering method has specific application scenes and belongs to the technical field of building construction.
本发明涉及一种钢栈桥双壁钢围堰运输和快捷拼装下放施工方法,包括:步骤一:搭设钢栈桥;步骤二:分块预制加工完成双壁钢围堰壁体;步骤三:接长桩基施工使用过的钢护筒;步骤四:在钢护筒近水面高度处,在钢护筒上用型钢搭设拼装支架;步骤五:利用钢栈桥将钢围堰分块运输至现场,在拼装支架上拼装底节围堰;步骤六:钢护筒顶部安装下放系统;步骤七:整体提升底节围堰,拆除拼装支架;步骤八:整体下放底节围堰,底节围堰自浮于水面;步骤九:分块吊装上节围堰壁体,在底节围堰上接高上节围堰;步骤十:围堰内注水下沉至指定标高。本发明提高了大型双壁钢围堰拼装下放的精准度和便捷性,具有特定应用场景,属于建筑施工技术领域。
Steel trestle double-wall steel cofferdam transportation and rapid assembling and lowering construction method
The invention relates to a steel trestle double-wall steel cofferdam transporting and rapid assembling and lowering construction method. The method comprises the steps that firstly, a steel trestle is erected; secondly, the wall body of the double-wall steel cofferdam is prefabricated and machined in a blocking mode; thirdly, the steel casing used in pile foundation construction is lengthened; 4, erecting and assembling a bracket on the steel casing by using profile steel at the height of the steel casing close to the water surface; fifthly, the steel cofferdam is transported to the site in a blocking mode through a steel trestle, and a bottom section cofferdam is assembled on the assembling support; sixthly, a lowering system is installed on the top of the steel casing; seventhly, the bottom section cofferdam is integrally lifted, and the assembling supports are dismantled; eighthly, the bottom section cofferdam is integrally lowered, and the bottom section cofferdam automatically floats on the water surface; ninthly, the wall body of the upper section cofferdam is hoisted in a blocking mode, and the upper section cofferdam is heightened on the bottom section cofferdam; and tenthly, water is injected into the cofferdam to sink to the designated elevation. The large-scale double-wall steel cofferdam assembling and lowering precision and convenience are improved, and the large-scale double-wall steel cofferdam assembling and lowering method has specific application scenes and belongs to the technical field of building construction.
本发明涉及一种钢栈桥双壁钢围堰运输和快捷拼装下放施工方法,包括:步骤一:搭设钢栈桥;步骤二:分块预制加工完成双壁钢围堰壁体;步骤三:接长桩基施工使用过的钢护筒;步骤四:在钢护筒近水面高度处,在钢护筒上用型钢搭设拼装支架;步骤五:利用钢栈桥将钢围堰分块运输至现场,在拼装支架上拼装底节围堰;步骤六:钢护筒顶部安装下放系统;步骤七:整体提升底节围堰,拆除拼装支架;步骤八:整体下放底节围堰,底节围堰自浮于水面;步骤九:分块吊装上节围堰壁体,在底节围堰上接高上节围堰;步骤十:围堰内注水下沉至指定标高。本发明提高了大型双壁钢围堰拼装下放的精准度和便捷性,具有特定应用场景,属于建筑施工技术领域。
Steel trestle double-wall steel cofferdam transportation and rapid assembling and lowering construction method
一种钢栈桥双壁钢围堰运输和快捷拼装下放施工方法
XU ZHEHUI (author) / WU YUHUA (author) / XU HONGZUO (author) / CHEN KUI (author) / FAN HAOBIN (author) / SHUKYO (author) / WANG CONG (author) / WANG GANG (author) / CHEN ZHIXING (author) / OU JIALIN (author)
2022-07-29
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|Double-wall steel cofferdam structure construction method and double-wall steel cofferdam structure
European Patent Office | 2023
|European Patent Office | 2023
|