A platform for research: civil engineering, architecture and urbanism
Construction method for integrally lifting and installing cable crane
The invention discloses an integral lifting and mounting construction method for a cable crane, which comprises the following steps: assembling the cable crane into three integral components on the field ground, lifting the three integral components to a designed mounting position at one time by adopting an auxiliary lifting facility, fixing two of the integral components with a main cable, then mounting a middle component, and finally mounting the middle component on the main cable; and finally, the cable-loaded crane is installed. Most cable crane installation work is adjusted to field installation, one-time hoisting is achieved, field aerial work can be reduced to a great extent, the main line construction period is shortened, and safety risks are reduced.
本发明公开了一种缆载吊机整体提升安装施工方法,包括:将缆载吊机在现场地面上组拼为三个整体构件后,采用辅助提升设施将三个整体构件一次提升至设计安装位置,先将其中两个整体构件与主缆固定后,然后安装中间构件,最终实现缆载吊机安装。本发明将大部分缆载吊机安装工作调整至场内安装,一次吊装到位,可很大程度减少现场高空作业工作,节约主线工期,降低安全风险。
Construction method for integrally lifting and installing cable crane
The invention discloses an integral lifting and mounting construction method for a cable crane, which comprises the following steps: assembling the cable crane into three integral components on the field ground, lifting the three integral components to a designed mounting position at one time by adopting an auxiliary lifting facility, fixing two of the integral components with a main cable, then mounting a middle component, and finally mounting the middle component on the main cable; and finally, the cable-loaded crane is installed. Most cable crane installation work is adjusted to field installation, one-time hoisting is achieved, field aerial work can be reduced to a great extent, the main line construction period is shortened, and safety risks are reduced.
本发明公开了一种缆载吊机整体提升安装施工方法,包括:将缆载吊机在现场地面上组拼为三个整体构件后,采用辅助提升设施将三个整体构件一次提升至设计安装位置,先将其中两个整体构件与主缆固定后,然后安装中间构件,最终实现缆载吊机安装。本发明将大部分缆载吊机安装工作调整至场内安装,一次吊装到位,可很大程度减少现场高空作业工作,节约主线工期,降低安全风险。
Construction method for integrally lifting and installing cable crane
一种缆载吊机整体提升安装施工方法
ZHANG YONGTAO (author) / PAN GUILIN (author) / CHEN MING (author) / YANG HAIZHONG (author) / PAN JI (author) / PENG CHENGMING (author) / PENG ZHIHUI (author) / XU XIN (author) / HU WEI (author) / LI MIAN (author)
2022-11-08
Patent
Electronic Resource
Chinese
Method for integrally lifting and installing steel platforms in limited space
European Patent Office | 2020
|Special device for integrally lifting, installing and constructing fabricated curtain wall
European Patent Office | 2022
|Construction method for installing bridge deck prefabricated slabs through cable crane
European Patent Office | 2023
|European Patent Office | 2022
|