Large-section independent batter post construction method based on BIM technology
The invention discloses a large-section independent batter post construction method based on a BIM technology, and the method specifically comprises the following steps: S1, building a BIM model of a batter post according to a construction blueprint, and setting a reference point; s2, establishing a BIM model of the inclined column tie structure, and positioning the pre-embedded tie bars and the tie frame; s3, establishing a BIM model of the inclined column outer frame, and positioning a falling point of the inclined column outer frame; s4, performing three-dimensional visual disclosure on technicians and constructors through the BIM models; s5, surveying, setting-out and construction are conducted on the construction site; s6, the position of the concrete vibrating rod is determined by combining the BIM model with the working radius of the used concrete vibrating rod; s7, a formwork is built on the outer side of the inclined column steel bar structure; s8, pouring and vibrating batter post concrete; s9, after construction is completed, acceptance check is conducted according to the BIM model; according to the method, the three-dimensional coordinates of the key nodes can be accurately positioned, so that the batter post construction quality is high, the construction is safer, the construction cost is effectively saved, and the construction period is shortened.
本发明公开了一种基于BIM技术的大截面独立斜柱施工方法,具体包括以下步骤:S1,根据施工蓝图建立斜柱的BIM模型,设立基准点;S2,建立斜柱拉结结构的BIM模型,对预埋拉结钢筋和拉结框进行定位;S3,建立斜柱外架的BIM模型,对斜柱外架的落点进行定位;S4、通过各BIM模型对技术员和施工人员进行三维可视化交底;S5、在施工现场进行测量放线和施工;S6、通过BIM模型结合所使用的混凝土振捣棒的作业半径确定混凝土振捣棒的位置;S7、在斜柱钢筋结构的外侧搭建模板;S8、进行斜柱混凝土的浇筑、振捣;S9、施工完成后,依据BIM模型进行验收;本发明可精确定位关键节点的三维坐标,使得斜柱施工质量高、施工更加安全,有效节约了施工成本,缩短了施工周期。
Large-section independent batter post construction method based on BIM technology
The invention discloses a large-section independent batter post construction method based on a BIM technology, and the method specifically comprises the following steps: S1, building a BIM model of a batter post according to a construction blueprint, and setting a reference point; s2, establishing a BIM model of the inclined column tie structure, and positioning the pre-embedded tie bars and the tie frame; s3, establishing a BIM model of the inclined column outer frame, and positioning a falling point of the inclined column outer frame; s4, performing three-dimensional visual disclosure on technicians and constructors through the BIM models; s5, surveying, setting-out and construction are conducted on the construction site; s6, the position of the concrete vibrating rod is determined by combining the BIM model with the working radius of the used concrete vibrating rod; s7, a formwork is built on the outer side of the inclined column steel bar structure; s8, pouring and vibrating batter post concrete; s9, after construction is completed, acceptance check is conducted according to the BIM model; according to the method, the three-dimensional coordinates of the key nodes can be accurately positioned, so that the batter post construction quality is high, the construction is safer, the construction cost is effectively saved, and the construction period is shortened.
本发明公开了一种基于BIM技术的大截面独立斜柱施工方法,具体包括以下步骤:S1,根据施工蓝图建立斜柱的BIM模型,设立基准点;S2,建立斜柱拉结结构的BIM模型,对预埋拉结钢筋和拉结框进行定位;S3,建立斜柱外架的BIM模型,对斜柱外架的落点进行定位;S4、通过各BIM模型对技术员和施工人员进行三维可视化交底;S5、在施工现场进行测量放线和施工;S6、通过BIM模型结合所使用的混凝土振捣棒的作业半径确定混凝土振捣棒的位置;S7、在斜柱钢筋结构的外侧搭建模板;S8、进行斜柱混凝土的浇筑、振捣;S9、施工完成后,依据BIM模型进行验收;本发明可精确定位关键节点的三维坐标,使得斜柱施工质量高、施工更加安全,有效节约了施工成本,缩短了施工周期。
Large-section independent batter post construction method based on BIM technology
一种基于BIM技术的大截面独立斜柱施工方法
GAO HESHENG (author) / SUN CONGCONG (author) / CAO QIJIA (author)
2022-11-08
Patent
Electronic Resource
Chinese
Construction method of large-section concrete batter post
European Patent Office | 2024
|European Patent Office | 2024
|Construction method of large-diameter circular steel reinforced concrete batter post
European Patent Office | 2023
|