Small-radius curve cast-in-place continuous box girder construction method
The invention discloses a construction method of a small-radius curve cast-in-place continuous box girder. The construction method comprises the following steps of foundation treatment, replacement and filling treatment of a river valley section in the middle of a girder body and foundation pit treatment on the periphery of a pier column. The construction method comprises the steps of construction of a support, construction and calculation of a support system, reinforcement and protection of the support, and finally installation of a formwork. Performing a pre-pressing test on the bracket; the cast-in-place beam is constructed, steel bars are bound, concrete is poured, and the concrete is cured after pouring; the formwork and the support are sequentially dismantled after concrete is poured, through the series of construction methods, compared with a prefabricated box girder, the pouring time is greatly shortened while the quality of the concrete cast-in-place beam is guaranteed, and the production speed of the small-radius cast-in-place beam is remarkably increased.
本发明公开了小半径曲线现浇连续箱梁施工工法,包括以下步骤地基处理,梁体中间位于河谷段的换填处理和墩柱四周的基坑处理;支架的搭设,支架体系的搭设和计算,支架的加固和防护,最后进行模板的安装;支架进行预压的测试;现浇梁的施工,对钢筋进行绑扎,混凝土进行浇筑,浇筑后对混凝土进行养护;对混凝土浇筑之后对模板和支架进行依次拆除,通过此种一系列的施工方法,该技术在模板和砼的浇筑与预制箱梁相比,在保证了混凝土现浇梁的质量的同时大大的缩短了浇筑的时间,显著加快了小半径现浇梁的生产速度。
Small-radius curve cast-in-place continuous box girder construction method
The invention discloses a construction method of a small-radius curve cast-in-place continuous box girder. The construction method comprises the following steps of foundation treatment, replacement and filling treatment of a river valley section in the middle of a girder body and foundation pit treatment on the periphery of a pier column. The construction method comprises the steps of construction of a support, construction and calculation of a support system, reinforcement and protection of the support, and finally installation of a formwork. Performing a pre-pressing test on the bracket; the cast-in-place beam is constructed, steel bars are bound, concrete is poured, and the concrete is cured after pouring; the formwork and the support are sequentially dismantled after concrete is poured, through the series of construction methods, compared with a prefabricated box girder, the pouring time is greatly shortened while the quality of the concrete cast-in-place beam is guaranteed, and the production speed of the small-radius cast-in-place beam is remarkably increased.
本发明公开了小半径曲线现浇连续箱梁施工工法,包括以下步骤地基处理,梁体中间位于河谷段的换填处理和墩柱四周的基坑处理;支架的搭设,支架体系的搭设和计算,支架的加固和防护,最后进行模板的安装;支架进行预压的测试;现浇梁的施工,对钢筋进行绑扎,混凝土进行浇筑,浇筑后对混凝土进行养护;对混凝土浇筑之后对模板和支架进行依次拆除,通过此种一系列的施工方法,该技术在模板和砼的浇筑与预制箱梁相比,在保证了混凝土现浇梁的质量的同时大大的缩短了浇筑的时间,显著加快了小半径现浇梁的生产速度。
Small-radius curve cast-in-place continuous box girder construction method
小半径曲线现浇连续箱梁施工工法
XU TAO (author) / ZHANG HONG (author) / SHI XIAOFENG (author) / DENG CHAO (author) / WANG HOUFENG (author)
2022-11-25
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Small-radius curve cast-in-place box girder construction method
European Patent Office | 2023
|Cast-in-place prestressed concrete continuous box girder construction method
European Patent Office | 2020
|Cast-in-place box girder support system and cast-in-place box girder construction method
European Patent Office | 2024
|