Construction method for intercepting concrete of different grades at beam-column joint
The invention discloses a construction method for intercepting concrete of different grades at a beam-column joint. The method comprises the steps that S1, a user is familiar with a design drawing before construction, a detailed concrete interception construction scheme is compiled, a proper number of construction workers are provided according to factors such as the engineering amount and the operation environment, and resources such as materials and tools needed in construction are prepared; s2, a power trolley combination is installed; s3, steel wire meshes are fully distributed on the beam side and the lower protection layer area through a power trolley combination; s4, placing a steel wire mesh or a fast-easy closing-up mesh in the beam; s5, asymmetric supporting rods are installed; s6, placing a steel wire mesh or a fast-easy closing-up mesh on the plate surface and the upper part of the beam; and S7, the card type intercepting device is installed. The blocking device plays a role in intercepting concrete seepage at protection layers at the bottom and the two sides of the beam, the interior of beam steel bars, the plate face and the protection layer on the upper portion of the beam.
本发明公开梁柱节点处不同标号混凝土拦截施工方法,包括如下步骤;S1、施工前熟悉设计图纸,编制详细的混凝土拦截施工方案,根据工程量的大小、作业环境等因素配备适当数量的施工作业人员,准备施工中需要的材料及工器具等资源;S2、安装动力小车组合;S3、通过动力小车组合将钢丝网布满梁侧及下部保护层区域;S4、梁内放置钢丝网或快易收口网;S5、安装不对称支撑杆;S6、板面上及梁上部放置钢丝网或快易收口网;S7、安装卡片式拦截装置,本发明起到对梁底及两侧保护层处、梁钢筋内部、板面及梁上部保护层处混凝土渗流的拦截作用。
Construction method for intercepting concrete of different grades at beam-column joint
The invention discloses a construction method for intercepting concrete of different grades at a beam-column joint. The method comprises the steps that S1, a user is familiar with a design drawing before construction, a detailed concrete interception construction scheme is compiled, a proper number of construction workers are provided according to factors such as the engineering amount and the operation environment, and resources such as materials and tools needed in construction are prepared; s2, a power trolley combination is installed; s3, steel wire meshes are fully distributed on the beam side and the lower protection layer area through a power trolley combination; s4, placing a steel wire mesh or a fast-easy closing-up mesh in the beam; s5, asymmetric supporting rods are installed; s6, placing a steel wire mesh or a fast-easy closing-up mesh on the plate surface and the upper part of the beam; and S7, the card type intercepting device is installed. The blocking device plays a role in intercepting concrete seepage at protection layers at the bottom and the two sides of the beam, the interior of beam steel bars, the plate face and the protection layer on the upper portion of the beam.
本发明公开梁柱节点处不同标号混凝土拦截施工方法,包括如下步骤;S1、施工前熟悉设计图纸,编制详细的混凝土拦截施工方案,根据工程量的大小、作业环境等因素配备适当数量的施工作业人员,准备施工中需要的材料及工器具等资源;S2、安装动力小车组合;S3、通过动力小车组合将钢丝网布满梁侧及下部保护层区域;S4、梁内放置钢丝网或快易收口网;S5、安装不对称支撑杆;S6、板面上及梁上部放置钢丝网或快易收口网;S7、安装卡片式拦截装置,本发明起到对梁底及两侧保护层处、梁钢筋内部、板面及梁上部保护层处混凝土渗流的拦截作用。
Construction method for intercepting concrete of different grades at beam-column joint
梁柱节点处不同标号混凝土拦截施工方法
CHEN GANG (author) / ZHONG SHUAI (author) / XIAO HAN (author) / TENG XIAOJUN (author) / QUAN YOUWEI (author) / WANG YAFEI (author) / XIONG RUIMING (author) / TAN LUE (author) / TANG LEI (author)
2023-04-11
Patent
Electronic Resource
Chinese
Method for intercepting concrete of different grades at beam-column joint
European Patent Office | 2021
|Beam and column joint concrete intercepting structure and construction method thereof
European Patent Office | 2023
|Wall column beam joint concrete pouring construction method with different strength grades
European Patent Office | 2022
|Beam column joint concrete wire mesh intercepting device and method
European Patent Office | 2023
|Beam column joint core area high-grade concrete intercepting system and construction method