Construction treatment method for resisting basement floating
The invention discloses a construction processing method for resisting basement floating, which relates to the field of building construction, adopts different anti-floating measures in different construction stages, and mainly comprises the following steps: a construction design stage: carrying out anti-floating measure design according to an actual underground water level line and geological condition exploration data; in the middle stage of construction, anti-floating treatment is conducted through a loading method, a balance method and enhanced dewatering and drainage measures; and in the later stage of construction, anti-floating treatment is conducted through pressure relief, underground water level lowering, grouting, anti-floating anchor rod increasing and structure reinforcing. According to the method, different confrontation measures are taken for the upward floating condition of the basement at different construction stages, so that building deformation caused by upward floating of the basement is effectively prevented.
本发明公开了一种用于抵抗地下室上浮的施工处理方法,涉及建筑施工领域,其在不同施工阶段采用不同抗浮措施,主要包括:施工设计阶段,根据实际地下水位线和地质情况勘探数据进行抗浮措施设计;施工中期阶段,通过加载法、平衡法以及加强降排水措施进行抗浮处理;施工后期阶段,通过泄压、降低地下水位、注浆、增加抗浮锚杆和结构加固进行抗浮处理。本发明通过在不同施工阶段,对地下室的上浮情况采取不同的对抗措施,从而有效防止了地下室上浮导致的建筑物变形。
Construction treatment method for resisting basement floating
The invention discloses a construction processing method for resisting basement floating, which relates to the field of building construction, adopts different anti-floating measures in different construction stages, and mainly comprises the following steps: a construction design stage: carrying out anti-floating measure design according to an actual underground water level line and geological condition exploration data; in the middle stage of construction, anti-floating treatment is conducted through a loading method, a balance method and enhanced dewatering and drainage measures; and in the later stage of construction, anti-floating treatment is conducted through pressure relief, underground water level lowering, grouting, anti-floating anchor rod increasing and structure reinforcing. According to the method, different confrontation measures are taken for the upward floating condition of the basement at different construction stages, so that building deformation caused by upward floating of the basement is effectively prevented.
本发明公开了一种用于抵抗地下室上浮的施工处理方法,涉及建筑施工领域,其在不同施工阶段采用不同抗浮措施,主要包括:施工设计阶段,根据实际地下水位线和地质情况勘探数据进行抗浮措施设计;施工中期阶段,通过加载法、平衡法以及加强降排水措施进行抗浮处理;施工后期阶段,通过泄压、降低地下水位、注浆、增加抗浮锚杆和结构加固进行抗浮处理。本发明通过在不同施工阶段,对地下室的上浮情况采取不同的对抗措施,从而有效防止了地下室上浮导致的建筑物变形。
Construction treatment method for resisting basement floating
一种用于抵抗地下室上浮的施工处理方法
CHENG JIALIANG (author) / JIA LONGFEI (author)
2023-04-28
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Water-carrying floating-reducing and floating-resisting system and basement structure
European Patent Office | 2021
|Basement anti-floating structure and construction method thereof
European Patent Office | 2021
|Anti-floating dewatering method in basement construction period
European Patent Office | 2023
|Basement anti-floating system and construction technology
European Patent Office | 2024
|Basement anti-floating structure and construction method thereof
European Patent Office | 2020
|