A platform for research: civil engineering, architecture and urbanism
Construction method for bubble mixed light filling soil
The invention discloses a construction method for bubble mixed light filling soil. The construction method comprises the following steps: preparing the bubble mixed light filling soil; constructing an embankment foundation pit and an embankment foundation at the slope body corresponding to the roadbed so as to form a to-be-poured area on one side of the slope body; a panel foundation is built in the to-be-poured area, and a prefabricated panel is installed on the side, away from the slope body, of the panel foundation; the bubble mixed light filling soil is poured between the prefabricated panel and the slope body, so that a bubble mixed light filling soil layer is formed in the to-be-poured area; and constructing supporting facilities of a roadbed on the bubble mixed light filling soil layer to finish embankment construction. According to the method, the roadbed of the expressway is filled with the bubble mixed light filling soil, compared with common roadbed filling soil, the mass of the bubble mixed light filling soil is easier to control compared with the mass of filled soil and stone, the bubble mixed light filling soil is not prone to being affected by rainwater, and the construction cost is saved.
本发明公开了一种用于气泡混合轻质填筑土的施工方法,包括如下步骤:制备气泡混合轻质填筑土;在路基所对应的坡体处施作路堤基坑及路堤基础,以在所述坡体的一侧形成待浇筑区;在所述待浇筑区修筑面板基础,并在所述面板基础远离所述坡体的一侧安装预制面板;在所述预制面板与所述坡体之间浇筑所述气泡混合轻质填筑土,以在所述待浇筑区形成气泡混合轻质填筑土层;在所述气泡混合轻质填筑土层施作路基的配套设施,完成路堤施工。本发明通过利用气泡混合轻质填筑土对高速公路的路基进行填筑,相较于普通路基填筑土,气泡混合轻质填筑土的质量比填筑土石的质量易控制,且不易受雨水影响,节约施工成本。
Construction method for bubble mixed light filling soil
The invention discloses a construction method for bubble mixed light filling soil. The construction method comprises the following steps: preparing the bubble mixed light filling soil; constructing an embankment foundation pit and an embankment foundation at the slope body corresponding to the roadbed so as to form a to-be-poured area on one side of the slope body; a panel foundation is built in the to-be-poured area, and a prefabricated panel is installed on the side, away from the slope body, of the panel foundation; the bubble mixed light filling soil is poured between the prefabricated panel and the slope body, so that a bubble mixed light filling soil layer is formed in the to-be-poured area; and constructing supporting facilities of a roadbed on the bubble mixed light filling soil layer to finish embankment construction. According to the method, the roadbed of the expressway is filled with the bubble mixed light filling soil, compared with common roadbed filling soil, the mass of the bubble mixed light filling soil is easier to control compared with the mass of filled soil and stone, the bubble mixed light filling soil is not prone to being affected by rainwater, and the construction cost is saved.
本发明公开了一种用于气泡混合轻质填筑土的施工方法,包括如下步骤:制备气泡混合轻质填筑土;在路基所对应的坡体处施作路堤基坑及路堤基础,以在所述坡体的一侧形成待浇筑区;在所述待浇筑区修筑面板基础,并在所述面板基础远离所述坡体的一侧安装预制面板;在所述预制面板与所述坡体之间浇筑所述气泡混合轻质填筑土,以在所述待浇筑区形成气泡混合轻质填筑土层;在所述气泡混合轻质填筑土层施作路基的配套设施,完成路堤施工。本发明通过利用气泡混合轻质填筑土对高速公路的路基进行填筑,相较于普通路基填筑土,气泡混合轻质填筑土的质量比填筑土石的质量易控制,且不易受雨水影响,节约施工成本。
Construction method for bubble mixed light filling soil
用于气泡混合轻质填筑土的施工方法
MENG XIAOKANG (author) / ZHANG HUAJIAN (author) / ZHAO SHUNGUO (author) / ZHANG YI (author) / YU LEI (author) / WANG YUANXIANG (author) / MOU CHUNMING (author) / YANG HAIBO (author) / GUO ZHIFENG (author)
2023-07-18
Patent
Electronic Resource
Chinese
Construction method of bubble mixed light soil embankment
European Patent Office | 2023
|