Construction method of integrated attached lifting scaffold
The invention discloses a construction method of an integrated attached lifting scaffold, which belongs to the field of building construction and comprises the following steps: preparing construction technical data and tool equipment; a construction scheme and construction site data information are verified, and a frame arrangement scheme and a standard layer pre-burying scheme are determined; construction technology disclosure; setting up an operation platform; checking and accepting the operation platform; assembling a bottom truss on the ground; hoisting a bottom truss section by section; erecting and pre-burying a main frame; protective facility installation and main frame correction; mounting and debugging a lifting system; installing and debugging a control system; lifting the main frame; the main frame is dismantled; the main frames are assembled off site, then the main frames are combined at proper positions through a hoisting method, and the combined main frames can be lifted, so that the construction speed is higher, and the working efficiency is higher.
本发明公开了一种集成型附着式升降脚手架的施工方法,属于建筑施工领域,包括以下步骤:施工技术资料、工具设备准备;核实施工方案与施工现场数据信息,确定布架方案及标准层预埋方案;施工技术交底;操作平台搭设;操作平台验收;底部桁架地面组装;底部桁架分段吊装;主框架搭设及预埋;防护设施安装及主框架校正;升降系统安装及调试;控制系统安装调试;主框架提升;主框架拆除;本发明在场外对主框架进行组装,之后通过吊装的方法将主框架在合适的位置并进行组合,组合后的主框架能够进行升降,使得施工速度更快,工作效率更高。
Construction method of integrated attached lifting scaffold
The invention discloses a construction method of an integrated attached lifting scaffold, which belongs to the field of building construction and comprises the following steps: preparing construction technical data and tool equipment; a construction scheme and construction site data information are verified, and a frame arrangement scheme and a standard layer pre-burying scheme are determined; construction technology disclosure; setting up an operation platform; checking and accepting the operation platform; assembling a bottom truss on the ground; hoisting a bottom truss section by section; erecting and pre-burying a main frame; protective facility installation and main frame correction; mounting and debugging a lifting system; installing and debugging a control system; lifting the main frame; the main frame is dismantled; the main frames are assembled off site, then the main frames are combined at proper positions through a hoisting method, and the combined main frames can be lifted, so that the construction speed is higher, and the working efficiency is higher.
本发明公开了一种集成型附着式升降脚手架的施工方法,属于建筑施工领域,包括以下步骤:施工技术资料、工具设备准备;核实施工方案与施工现场数据信息,确定布架方案及标准层预埋方案;施工技术交底;操作平台搭设;操作平台验收;底部桁架地面组装;底部桁架分段吊装;主框架搭设及预埋;防护设施安装及主框架校正;升降系统安装及调试;控制系统安装调试;主框架提升;主框架拆除;本发明在场外对主框架进行组装,之后通过吊装的方法将主框架在合适的位置并进行组合,组合后的主框架能够进行升降,使得施工速度更快,工作效率更高。
Construction method of integrated attached lifting scaffold
一种集成型附着式升降脚手架的施工方法
YUAN KEKE (author) / ZHANG YONGLI (author) / SHI JUNTAI (author) / WANG QINQIN (author) / SONG YUSHENG (author) / LIU MANKU (author) / CHEN ZHUO (author) / DU YOUXIU (author) / NIU CHAO (author)
2023-08-11
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Integrated attached lifting scaffold and construction method thereof