Construction method for using enclosure separation pile as engineering pile
The invention relates to the field of building construction, and discloses a construction method for using an enclosure separation pile as an engineering pile, which comprises the following steps: S1, foundation pit zoning; s2, applying and driving separation piles; s3, determining a construction batch; s4, earth excavation and basement construction are conducted, specifically, excavation of the first-batch excavation area is completed, a first bottom plate is arranged at the bottom of the first-batch excavation area, a basement is constructed to +/-0 on the first bottom plate, excavation of the adjacent second-batch excavation area is started, a second bottom plate is arranged at the bottom of the second-batch excavation area, and a basement is constructed to +/-0 on the second bottom plate; s5, the separation piles are broken and removed, specifically, the separation piles between the adjacent foundation pits constructed in two batches are broken and removed to the bottom of the first bottom plate; and S6, the bottom plates are communicated, a third bottom plate is arranged between the first bottom plate and the second bottom plate, and after breaking, the remaining separation piles are fixed into the third bottom plate and become anti-pulling engineering piles. The partition pile can become a permanent and temporary combined structure, the partition pile is reused, and the construction cost of a project is reduced.
本申请涉及建筑施工的领域,公开了一种围护分隔桩用作工程桩的施工方法,其包括如下步骤:S1:基坑分区;S2:施打分隔桩;S3:确定施工批次;S4:土方开挖及地下室施工,第一批次开挖区挖掘完成,于第一批次开挖区底部设置第一底板并于第一底板上施工地下室至±0,相邻第二批次开挖区开始挖掘,并于第二批次开挖区底部设置第二底板并于第二底板上施工地下室至±0;S5:破除分隔桩,将先后两批次施工的相邻基坑间的分隔桩破除至第一底板底部;S6:底板连通,于第一底板与第二地板之间设置第三底板,破除后剩余分隔桩固定于第三底板内并成为抗拔工程桩。本申请具有能够使分隔桩成为永临结合结构,将分隔桩再次利用,降低工程的施工成本。
Construction method for using enclosure separation pile as engineering pile
The invention relates to the field of building construction, and discloses a construction method for using an enclosure separation pile as an engineering pile, which comprises the following steps: S1, foundation pit zoning; s2, applying and driving separation piles; s3, determining a construction batch; s4, earth excavation and basement construction are conducted, specifically, excavation of the first-batch excavation area is completed, a first bottom plate is arranged at the bottom of the first-batch excavation area, a basement is constructed to +/-0 on the first bottom plate, excavation of the adjacent second-batch excavation area is started, a second bottom plate is arranged at the bottom of the second-batch excavation area, and a basement is constructed to +/-0 on the second bottom plate; s5, the separation piles are broken and removed, specifically, the separation piles between the adjacent foundation pits constructed in two batches are broken and removed to the bottom of the first bottom plate; and S6, the bottom plates are communicated, a third bottom plate is arranged between the first bottom plate and the second bottom plate, and after breaking, the remaining separation piles are fixed into the third bottom plate and become anti-pulling engineering piles. The partition pile can become a permanent and temporary combined structure, the partition pile is reused, and the construction cost of a project is reduced.
本申请涉及建筑施工的领域,公开了一种围护分隔桩用作工程桩的施工方法,其包括如下步骤:S1:基坑分区;S2:施打分隔桩;S3:确定施工批次;S4:土方开挖及地下室施工,第一批次开挖区挖掘完成,于第一批次开挖区底部设置第一底板并于第一底板上施工地下室至±0,相邻第二批次开挖区开始挖掘,并于第二批次开挖区底部设置第二底板并于第二底板上施工地下室至±0;S5:破除分隔桩,将先后两批次施工的相邻基坑间的分隔桩破除至第一底板底部;S6:底板连通,于第一底板与第二地板之间设置第三底板,破除后剩余分隔桩固定于第三底板内并成为抗拔工程桩。本申请具有能够使分隔桩成为永临结合结构,将分隔桩再次利用,降低工程的施工成本。
Construction method for using enclosure separation pile as engineering pile
一种围护分隔桩用作工程桩的施工方法
SHI YANG (author) / CHEN KAI (author) / YOU PENGCHAO (author) / SUN HAIWEI (author) / HUANG YAJUN (author) / KE RUI (author) / LI YING (author) / MEI XIAOFENG (author) / YAN JIXIANG (author)
2023-09-05
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2015
|Building concrete pipe pile precast pile enclosure structure construction system
European Patent Office | 2024
|European Patent Office | 2023
|