A platform for research: civil engineering, architecture and urbanism
Prefabricated inverted arch design and construction method for preventing and treating heaving floor deformation of tunnel
The invention discloses a prefabricated inverted arch design and construction method for preventing and treating tunnel floor heaving deformation. The construction method of a prefabricated inverted arch comprises the following steps that (1) the size of the prefabricated inverted arch is designed; (2) the shape of a prefabricated inverted arch is designed; (3) processing and manufacturing a prefabricated inverted arch; (4) the prefabricated inverted arch is installed on the construction site; and 5) pavement paving. The prefabricated inverted arch comprises a left prefabricated block, a right prefabricated block and a center prefabricated block, the left prefabricated block is laid on the left side of the tunnel base, the right prefabricated block is laid on the right side of the tunnel base, the center prefabricated block is laid between the left prefabricated block and the right prefabricated block, and the sum of the lengths of the top faces of the left prefabricated block, the right prefabricated block and the center prefabricated block is the width of the horizontal plane of the tunnel; the contact surfaces among the left prefabricated block, the right prefabricated block and the central prefabricated block are respectively provided with a prefabricated assembly type joint, and all the prefabricated blocks are in grouting connection after being positioned and butted through the prefabricated assembly type joints.
本发明公开了一种防治隧道底鼓变形的预制仰拱设计及施工方法,预制仰拱的施工方法包括以下步骤:1)预制仰拱尺寸设计;2)预制仰拱形状设计;3)预制仰拱加工制作;4)施工现场安装预制仰拱;5)路面铺设。预制仰拱包括左预制块、右预制块和中心预制块,左预制块铺设于隧道基底左侧,右预制块铺设于隧道基底右侧,中心预制块铺设于左预制块和右预制块之间,左预制块、右预制块及中心预制块顶面的长度之和为隧道水平面的宽度;左预制块、右预制块及中心预制块相互之间的接触面上分别设有预制装配式接头,各预制块分别通过预制装配式接头定位对接后注浆连接。
Prefabricated inverted arch design and construction method for preventing and treating heaving floor deformation of tunnel
The invention discloses a prefabricated inverted arch design and construction method for preventing and treating tunnel floor heaving deformation. The construction method of a prefabricated inverted arch comprises the following steps that (1) the size of the prefabricated inverted arch is designed; (2) the shape of a prefabricated inverted arch is designed; (3) processing and manufacturing a prefabricated inverted arch; (4) the prefabricated inverted arch is installed on the construction site; and 5) pavement paving. The prefabricated inverted arch comprises a left prefabricated block, a right prefabricated block and a center prefabricated block, the left prefabricated block is laid on the left side of the tunnel base, the right prefabricated block is laid on the right side of the tunnel base, the center prefabricated block is laid between the left prefabricated block and the right prefabricated block, and the sum of the lengths of the top faces of the left prefabricated block, the right prefabricated block and the center prefabricated block is the width of the horizontal plane of the tunnel; the contact surfaces among the left prefabricated block, the right prefabricated block and the central prefabricated block are respectively provided with a prefabricated assembly type joint, and all the prefabricated blocks are in grouting connection after being positioned and butted through the prefabricated assembly type joints.
本发明公开了一种防治隧道底鼓变形的预制仰拱设计及施工方法,预制仰拱的施工方法包括以下步骤:1)预制仰拱尺寸设计;2)预制仰拱形状设计;3)预制仰拱加工制作;4)施工现场安装预制仰拱;5)路面铺设。预制仰拱包括左预制块、右预制块和中心预制块,左预制块铺设于隧道基底左侧,右预制块铺设于隧道基底右侧,中心预制块铺设于左预制块和右预制块之间,左预制块、右预制块及中心预制块顶面的长度之和为隧道水平面的宽度;左预制块、右预制块及中心预制块相互之间的接触面上分别设有预制装配式接头,各预制块分别通过预制装配式接头定位对接后注浆连接。
Prefabricated inverted arch design and construction method for preventing and treating heaving floor deformation of tunnel
一种防治隧道底鼓变形的预制仰拱设计及施工方法
LIU JIHONG (author) / CAI SHUHONG (author) / WU HONGGANG (author) / ZHOU XINLU (author) / SHU CHENGXING (author) / ZHAO TIANYU (author) / DUAN RUIKAI (author) / JIA GANGLONG (author) / LIU CHUNLI (author) / YI ZHONGQIANG (author)
2023-09-12
Patent
Electronic Resource
Chinese
European Patent Office | 2015
|