Method for arranging tower crane foundation and tower crane foundation structure
The invention discloses a method for arranging a tower crane foundation and a tower crane foundation structure, and relates to the technical field of construction buildings. The bottom plate structure is installed on the latticed columns of the multiple foundation pit supporting piles; the multiple supporting steel pipes are installed on the bottom plate structure, and the multiple transverse steel pipes and the multiple longitudinal steel pipes are bound to the multiple supporting steel pipes to form a supporting structure; the first formwork is installed at the top end of the supporting structure; supporting profile steel is welded to the latticed columns, the supporting profile steel is installed above the first formwork, and a tower crane foundation section is welded to the supporting profile steel; reinforcing steel bars are bound on the latticed columns to form a foundation reinforcing steel bar structure, and the foundation reinforcing steel bar structure is installed above the supporting profile steel; and concrete is poured to the first formwork, the tower crane foundation section and the foundation steel bar structure to form the tower crane foundation. By means of the method for arranging the tower crane foundation, the latticed columns of the foundation pit supporting piles can be fully utilized, the construction cost is reduced, and the construction time is shortened.
本发明公开了一种布置塔吊基础的方法及塔吊基础结构,涉及于施工建筑技术领域;将底板结构安装在多个基坑支撑桩的格构柱上;将多个支撑钢管安装在底板结构上,将多个横向钢管和多个纵向钢管绑扎在多个支撑钢管上,以形成支撑结构;将第一模板安装在支撑结构的顶端;将支撑型钢焊接在格构柱上,并使支撑型钢安装在第一模板的上方,将塔吊基础节焊接在支撑型钢上;将钢筋绑扎在格构柱上,以形成基础钢筋结构,并使基础钢筋结构安装在支撑型钢的上方;将混凝土浇筑在第一模板、塔吊基础节和基础钢筋结构处,以形成塔吊基础。通过该布置塔吊基础的方法能够充分利用基坑支撑桩的格构柱,降低施工成本,减少施工时长。
Method for arranging tower crane foundation and tower crane foundation structure
The invention discloses a method for arranging a tower crane foundation and a tower crane foundation structure, and relates to the technical field of construction buildings. The bottom plate structure is installed on the latticed columns of the multiple foundation pit supporting piles; the multiple supporting steel pipes are installed on the bottom plate structure, and the multiple transverse steel pipes and the multiple longitudinal steel pipes are bound to the multiple supporting steel pipes to form a supporting structure; the first formwork is installed at the top end of the supporting structure; supporting profile steel is welded to the latticed columns, the supporting profile steel is installed above the first formwork, and a tower crane foundation section is welded to the supporting profile steel; reinforcing steel bars are bound on the latticed columns to form a foundation reinforcing steel bar structure, and the foundation reinforcing steel bar structure is installed above the supporting profile steel; and concrete is poured to the first formwork, the tower crane foundation section and the foundation steel bar structure to form the tower crane foundation. By means of the method for arranging the tower crane foundation, the latticed columns of the foundation pit supporting piles can be fully utilized, the construction cost is reduced, and the construction time is shortened.
本发明公开了一种布置塔吊基础的方法及塔吊基础结构,涉及于施工建筑技术领域;将底板结构安装在多个基坑支撑桩的格构柱上;将多个支撑钢管安装在底板结构上,将多个横向钢管和多个纵向钢管绑扎在多个支撑钢管上,以形成支撑结构;将第一模板安装在支撑结构的顶端;将支撑型钢焊接在格构柱上,并使支撑型钢安装在第一模板的上方,将塔吊基础节焊接在支撑型钢上;将钢筋绑扎在格构柱上,以形成基础钢筋结构,并使基础钢筋结构安装在支撑型钢的上方;将混凝土浇筑在第一模板、塔吊基础节和基础钢筋结构处,以形成塔吊基础。通过该布置塔吊基础的方法能够充分利用基坑支撑桩的格构柱,降低施工成本,减少施工时长。
Method for arranging tower crane foundation and tower crane foundation structure
布置塔吊基础的方法及塔吊基础结构
XU XINXING (author) / TIAN JINGYANG (author) / WANG JINGBO (author) / LU DEHUI (author) / CHEN ZIGUI (author)
2023-11-28
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Tower crane foundation, tower crane and mounting method of tower crane