Reverse pile for underwater building and construction method thereof
The invention discloses a top-down pile for an underwater building and a construction method thereof, and is characterized in that the underwater building comprises a structure and the top-down pile positioned at the water bottom, and the structure comprises a pile interface; the construction method comprises the following main construction steps that (1) prefabrication of the structures and the reverse piles is completed; (2) the structure is conveyed and sinks to a set position, and underwater temporary positioning of the structure is completed; (3) construction of the reverse pile is completed in the pile connector; the construction method has the main advantages that the positioned structure is used as the reference, and the pile is driven in the pile connector, so that the positioning is accurate, the precision is high, the operation is convenient, and a cofferdam is not needed in the construction method.
本发明公开了一种用于水下建筑物的逆作桩及其施工法,其特征是所述的水下建筑物包括构筑物和位于水底的逆作桩,构筑物包括桩接口;其主要施工步骤如下:1)完成构筑物和逆作桩的预制;2)将构筑物运送且下沉至设定的位置,并完成其水下临时定位;3)在桩接口内完成逆作桩的施工;4)在无水的桩接口内,将逆作桩与构筑物连接;5)进行后续作业,直至完成建筑物的全部施工。本发明的主要优点是:以已定位的构筑物为基准,在桩接口内打桩,因此定位准确、精度高,操作方便,并且该工法实施中无需围堰。
Reverse pile for underwater building and construction method thereof
The invention discloses a top-down pile for an underwater building and a construction method thereof, and is characterized in that the underwater building comprises a structure and the top-down pile positioned at the water bottom, and the structure comprises a pile interface; the construction method comprises the following main construction steps that (1) prefabrication of the structures and the reverse piles is completed; (2) the structure is conveyed and sinks to a set position, and underwater temporary positioning of the structure is completed; (3) construction of the reverse pile is completed in the pile connector; the construction method has the main advantages that the positioned structure is used as the reference, and the pile is driven in the pile connector, so that the positioning is accurate, the precision is high, the operation is convenient, and a cofferdam is not needed in the construction method.
本发明公开了一种用于水下建筑物的逆作桩及其施工法,其特征是所述的水下建筑物包括构筑物和位于水底的逆作桩,构筑物包括桩接口;其主要施工步骤如下:1)完成构筑物和逆作桩的预制;2)将构筑物运送且下沉至设定的位置,并完成其水下临时定位;3)在桩接口内完成逆作桩的施工;4)在无水的桩接口内,将逆作桩与构筑物连接;5)进行后续作业,直至完成建筑物的全部施工。本发明的主要优点是:以已定位的构筑物为基准,在桩接口内打桩,因此定位准确、精度高,操作方便,并且该工法实施中无需围堰。
Reverse pile for underwater building and construction method thereof
用于水下建筑物的逆作桩及其施工法
2023-12-05
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Underwater tunnel with reverse pile pier and construction method thereof
European Patent Office | 2023
Underwater building with inverted pile and construction method thereof
European Patent Office | 2023
Underwater reverse bottom sealing hollow pile construction method
European Patent Office | 2023
|European Patent Office | 2024
|