The invention discloses an electric power calandria concrete anti-floating construction method, and particularly relates to the technical field of electric power calandria construction, and the electric power calandria concrete anti-floating construction method comprises the following specific steps: S1, data acquisition, S2, database establishment, S3, construction data processing and checking, S4, pipe ditch excavation, S5, cushion layer construction, S6, embedded bolt construction, S7, electric power calandria installation, S8, fixing assembly installation, S9, template support, and S10, concrete pouring inspection. And S11, concrete pouring is conducted. According to the invention, on-site pictures are transmitted to the database, and are compared with the reasons of buoyancy in the pouring process in the database and the pictures generated by the reasons, so that the construction can be optimized in a targeted manner according to the reasons of the buoyancy of the concrete of the electric power duct bank; therefore, the conditions of displacement of the electric power pipe bank, loosening of pipe hoops, fracture of joints, pipeline bending, slurry leakage and the like are avoided, and the construction quality and the construction progress are improved.
本发明公开了一种电力排管混凝土抗浮施工方法,具体涉及电力排管施工技术领域,包括具体步骤如下:S1、数据采集,S2、建立数据库,S3、施工数据处理核对,S4、管沟开挖,S5、垫层施工,S6、预埋螺栓施工,S7、电力排管安装,S8、固定组件安装,S9、模板支护,S10、混凝土浇筑检查,S11、混凝土浇筑。本发明根据现场图片输送到数据库中,与数据库中的浇筑过程中产生浮力的原因以及原因产生的图片进行比对,能够精确针对电力排管混凝土浮力原因针对性优化施工,从而避免电力排管位移、管箍松动、连接处断裂、管线弯曲、漏浆等情况发生,提高施工质量以及施工进度。
Concrete anti-floating construction method for electric power duct bank
The invention discloses an electric power calandria concrete anti-floating construction method, and particularly relates to the technical field of electric power calandria construction, and the electric power calandria concrete anti-floating construction method comprises the following specific steps: S1, data acquisition, S2, database establishment, S3, construction data processing and checking, S4, pipe ditch excavation, S5, cushion layer construction, S6, embedded bolt construction, S7, electric power calandria installation, S8, fixing assembly installation, S9, template support, and S10, concrete pouring inspection. And S11, concrete pouring is conducted. According to the invention, on-site pictures are transmitted to the database, and are compared with the reasons of buoyancy in the pouring process in the database and the pictures generated by the reasons, so that the construction can be optimized in a targeted manner according to the reasons of the buoyancy of the concrete of the electric power duct bank; therefore, the conditions of displacement of the electric power pipe bank, loosening of pipe hoops, fracture of joints, pipeline bending, slurry leakage and the like are avoided, and the construction quality and the construction progress are improved.
本发明公开了一种电力排管混凝土抗浮施工方法,具体涉及电力排管施工技术领域,包括具体步骤如下:S1、数据采集,S2、建立数据库,S3、施工数据处理核对,S4、管沟开挖,S5、垫层施工,S6、预埋螺栓施工,S7、电力排管安装,S8、固定组件安装,S9、模板支护,S10、混凝土浇筑检查,S11、混凝土浇筑。本发明根据现场图片输送到数据库中,与数据库中的浇筑过程中产生浮力的原因以及原因产生的图片进行比对,能够精确针对电力排管混凝土浮力原因针对性优化施工,从而避免电力排管位移、管箍松动、连接处断裂、管线弯曲、漏浆等情况发生,提高施工质量以及施工进度。
Concrete anti-floating construction method for electric power duct bank
一种电力排管混凝土抗浮施工方法
ZHANG JIN (author) / WANG XIUTIAN (author) / ZHANG ZHANQI (author) / ZHANG WEIWEI (author)
2023-12-12
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
/
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
/
H02G
INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
,
Verlegen oder Installieren elektrischer Kabel oder Leitungen, Verlegen oder Installieren kombinierter optischer und elektrischer Kabel oder Leitungen
Construction method of concrete anti-floating anchor pile
European Patent Office | 2023
|Power cable duct bank working well and construction method thereof
European Patent Office | 2024
|Duct bank array installation and encapsulation construction method
European Patent Office | 2020
|Construction method for preventing floating of cable protection tube bank by wrapping concrete
European Patent Office | 2024
|