A platform for research: civil engineering, architecture and urbanism
Overhanging scaffold for super high-rise building construction
The invention relates to the field of scaffolds, in particular to an overhanging scaffold for super high-rise building construction, which comprises an upper floor slab arranged above a lower floor slab and further comprises two groups of first overhanging beams, second overhanging beams are arranged on the lower sides of the two groups of first overhanging beams, and bottom bracket plates are arranged on the lower sides of the two groups of second overhanging beams; second anchor rods and fastening bolts are arranged at the positions, close to the two ends, of the bottoms of the two sides of the two first cantilever beams in a penetrating mode. According to the cantilever scaffold, unstable supporting caused by loose connection between the cantilever scaffold and the lower floor in the using process can be avoided, the stability of the cantilever scaffold is improved, the safety is high, the cantilever scaffold has an efficient combined installation function, the installation difficulty of the cantilever scaffold is lowered, the disassembly and assembly efficiency of the cantilever scaffold is remarkably improved, and the construction cost is reduced. And the length of the cantilever scaffold can be stably changed, the convenient length adjusting function is achieved, and the application range of the cantilever scaffold is widened.
本发明涉及脚手架领域,具体为一种超高层建筑施工用的悬挑脚手架,包括设置在下楼板上方的上楼板,还包括两组第一悬挑梁,两组第一悬挑梁的下侧均设置有第二悬挑梁,两组第二悬挑梁的下侧均设置有底撑架板,两组第一悬挑梁的两侧底部靠近两端分别贯穿设置有第二锚杆和紧固螺栓;本发明能够避免悬挑脚手架在使用过程中与下楼板之间出现连接松动而造成支撑不稳,提高了悬挑脚手架的稳固性,安全性较高,且具有高效的组合安装功能,降低了悬挑脚手架的安装难度,显著提高了悬挑脚手架的拆装效率,并能够稳定地对悬挑脚手架的长度大小进行改变,具有便捷的长度调整功能,提高了悬挑脚手架的适用范围。
Overhanging scaffold for super high-rise building construction
The invention relates to the field of scaffolds, in particular to an overhanging scaffold for super high-rise building construction, which comprises an upper floor slab arranged above a lower floor slab and further comprises two groups of first overhanging beams, second overhanging beams are arranged on the lower sides of the two groups of first overhanging beams, and bottom bracket plates are arranged on the lower sides of the two groups of second overhanging beams; second anchor rods and fastening bolts are arranged at the positions, close to the two ends, of the bottoms of the two sides of the two first cantilever beams in a penetrating mode. According to the cantilever scaffold, unstable supporting caused by loose connection between the cantilever scaffold and the lower floor in the using process can be avoided, the stability of the cantilever scaffold is improved, the safety is high, the cantilever scaffold has an efficient combined installation function, the installation difficulty of the cantilever scaffold is lowered, the disassembly and assembly efficiency of the cantilever scaffold is remarkably improved, and the construction cost is reduced. And the length of the cantilever scaffold can be stably changed, the convenient length adjusting function is achieved, and the application range of the cantilever scaffold is widened.
本发明涉及脚手架领域,具体为一种超高层建筑施工用的悬挑脚手架,包括设置在下楼板上方的上楼板,还包括两组第一悬挑梁,两组第一悬挑梁的下侧均设置有第二悬挑梁,两组第二悬挑梁的下侧均设置有底撑架板,两组第一悬挑梁的两侧底部靠近两端分别贯穿设置有第二锚杆和紧固螺栓;本发明能够避免悬挑脚手架在使用过程中与下楼板之间出现连接松动而造成支撑不稳,提高了悬挑脚手架的稳固性,安全性较高,且具有高效的组合安装功能,降低了悬挑脚手架的安装难度,显著提高了悬挑脚手架的拆装效率,并能够稳定地对悬挑脚手架的长度大小进行改变,具有便捷的长度调整功能,提高了悬挑脚手架的适用范围。
Overhanging scaffold for super high-rise building construction
一种超高层建筑施工用的悬挑脚手架
XIAO HENG (author) / WANG ZHAOHE (author) / LIU SHANSHAN (author) / XU YONGFENG (author) / ZHANG CAIYUN (author) / WU SU-MING (author) / ZHUANG ZENGKAI (author) / BAO PENGCHENG (author) / DU CHAO (author)
2024-01-26
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Overhanging scaffold supporting system at overhanging balcony part of high-rise building
European Patent Office | 2023
|European Patent Office | 2024
|Demolition construction method for high-rise building roof overhanging structure
European Patent Office | 2022
|