Large-span net rack installation and construction method
The invention relates to the technical field of net rack construction, and discloses a large-span net rack installation and construction method which comprises the following steps: sequentially installing and connecting net racks among the top ends of a plurality of independent columns around a venue; firstly, mounting net rack units on the two sides of the venue in the first direction are mounted; selecting the net rack unit on one side of the first direction as a starting unit; the other net rack units are sequentially installed from the starting unit to the net rack unit on the other side in the first direction until overall installation of the net rack is completed, the net rack installation construction procedure is optimized, the internal site of a stadium can be flexibly and fully utilized, the requirement for interpenetrating operation of other procedures can be met, the construction efficiency is effectively improved, and the construction cost is reduced. And the construction period is ensured.
本发明涉及网架施工技术领域,公开了一种大跨度网架安装施工方法,包括以下步骤:在场馆四周的多个独立柱的顶端之间依次安装连接网架;先安装所述场馆在第一方向的两侧的安装网架单元;选取所述第一方向的一侧的所述网架单元作为起步单元;由所述起步单元向所述第一方向的另外一侧的网架单元依次安装其余的网架单元,直至完成网架的整体安装,本发明优化了网架安装施工工序,可灵活充分利用场馆内部场地,可满足其他工序穿插作业,有效地提高了施工效率,保证了施工工期。
Large-span net rack installation and construction method
The invention relates to the technical field of net rack construction, and discloses a large-span net rack installation and construction method which comprises the following steps: sequentially installing and connecting net racks among the top ends of a plurality of independent columns around a venue; firstly, mounting net rack units on the two sides of the venue in the first direction are mounted; selecting the net rack unit on one side of the first direction as a starting unit; the other net rack units are sequentially installed from the starting unit to the net rack unit on the other side in the first direction until overall installation of the net rack is completed, the net rack installation construction procedure is optimized, the internal site of a stadium can be flexibly and fully utilized, the requirement for interpenetrating operation of other procedures can be met, the construction efficiency is effectively improved, and the construction cost is reduced. And the construction period is ensured.
本发明涉及网架施工技术领域,公开了一种大跨度网架安装施工方法,包括以下步骤:在场馆四周的多个独立柱的顶端之间依次安装连接网架;先安装所述场馆在第一方向的两侧的安装网架单元;选取所述第一方向的一侧的所述网架单元作为起步单元;由所述起步单元向所述第一方向的另外一侧的网架单元依次安装其余的网架单元,直至完成网架的整体安装,本发明优化了网架安装施工工序,可灵活充分利用场馆内部场地,可满足其他工序穿插作业,有效地提高了施工效率,保证了施工工期。
Large-span net rack installation and construction method
一种大跨度网架安装施工方法
LEI ZIFENG (author) / CAO XUTAO (author) / ZHANG HONGCHUAN (author) / LI XIANGLONG (author) / PENG SHENG (author) / TANG RUILONG (author) / HE ZHI (author) / CEN BAIYI (author) / XIONG TAIRUI (author)
2024-03-08
Patent
Electronic Resource
Chinese
Construction method for starting installation of large-span arched net rack
European Patent Office | 2024
|Large-span steel structure net rack installation and construction technology
European Patent Office | 2023
|Construction method of large-span net rack starting rack
European Patent Office | 2021
|