A platform for research: civil engineering, architecture and urbanism
Net rack starting span installation method
The invention discloses a net rack starting span mounting method which comprises the following steps: assembling a starting grid, and stopping assembling when the starting grid is assembled to six bolt balls on an upper chord and seven bolt balls on a lower chord to form a net sheet; the two meshes are hoisted and installed at the two ends respectively; temporary supports are arranged at the positions of seventh, eighth, ninth, tenth and eleventh lower chord bolt balls in sequence, and sixth, seventh, eighth, ninth and tenth grids of an upper chord are installed; in the process, the temporary supports at the positions of the bolt balls of the lower chord are removed, the net rack is lifted through a crane, and the seventh, eighth, ninth, tenth and eleventh grids of the lower chord are installed; assembling a starting span middle block; and the hoisting point of the two assembled meshes is arranged at the eleventh bolt ball of the upper chord, and the middle block of the starting span is hoisted to be closed in the air. The method can quickly and accurately realize the starting span installation of the net rack.
本发明公开了一种网架起步跨安装方法,包括:将起步网格拼装,拼装到上弦6个螺栓球,下弦7个螺栓球时停止拼装,形成网片;将两个网片分别吊起安装在两端;依次在第七、八、九、十、十一个下弦螺栓球位置设置临时支撑,安装上弦第六、七、八、九、十格网格;并在上述过程中依次穿插“去掉下弦螺栓球位置临时支撑,用吊车提升网架,安装下弦第七、八、九、十、十一格网格”;拼装起步跨中间区块;将上述拼装后的两个网片的吊点设置在上弦第11个螺栓球处,吊起起步跨中间区块,进行空中合拢。本发明能快速准确的实现网架起步跨安装。
Net rack starting span installation method
The invention discloses a net rack starting span mounting method which comprises the following steps: assembling a starting grid, and stopping assembling when the starting grid is assembled to six bolt balls on an upper chord and seven bolt balls on a lower chord to form a net sheet; the two meshes are hoisted and installed at the two ends respectively; temporary supports are arranged at the positions of seventh, eighth, ninth, tenth and eleventh lower chord bolt balls in sequence, and sixth, seventh, eighth, ninth and tenth grids of an upper chord are installed; in the process, the temporary supports at the positions of the bolt balls of the lower chord are removed, the net rack is lifted through a crane, and the seventh, eighth, ninth, tenth and eleventh grids of the lower chord are installed; assembling a starting span middle block; and the hoisting point of the two assembled meshes is arranged at the eleventh bolt ball of the upper chord, and the middle block of the starting span is hoisted to be closed in the air. The method can quickly and accurately realize the starting span installation of the net rack.
本发明公开了一种网架起步跨安装方法,包括:将起步网格拼装,拼装到上弦6个螺栓球,下弦7个螺栓球时停止拼装,形成网片;将两个网片分别吊起安装在两端;依次在第七、八、九、十、十一个下弦螺栓球位置设置临时支撑,安装上弦第六、七、八、九、十格网格;并在上述过程中依次穿插“去掉下弦螺栓球位置临时支撑,用吊车提升网架,安装下弦第七、八、九、十、十一格网格”;拼装起步跨中间区块;将上述拼装后的两个网片的吊点设置在上弦第11个螺栓球处,吊起起步跨中间区块,进行空中合拢。本发明能快速准确的实现网架起步跨安装。
Net rack starting span installation method
一种网架起步跨安装方法
WU SHIJIONG (author) / YANG FAN (author) / DING MEIZHI (author) / YIN YAHONG (author) / TIAN CHENWEI (author)
2022-03-08
Patent
Electronic Resource
Chinese
Construction method for starting installation of large-span arched net rack
European Patent Office | 2024
|Construction method of large-span net rack starting rack
European Patent Office | 2021
|Rapid installation construction device for starting frame of steel structure large-span net rack
European Patent Office | 2023
|Large-span net rack installation and construction method
European Patent Office | 2024
|Construction method for applying spherical net rack support in large-span net rack starting frame
European Patent Office | 2021
|