One-time pouring construction method for spherical storage tank foundation column
The invention discloses a one-time pouring construction method for a spherical storage tank foundation column. The one-time pouring construction method comprises the following steps that S1, a column binding rib is installed on a foundation column buttress; s2, a plurality of pieces of fixed profile steel are installed on the foundation column buttress; s3, a mold is installed on the peripheral side of the foundation column buttress; s4, a sliding steel plate is installed; s5, foundation bolts are installed; s6, column concrete pouring is conducted; s7, after column concrete is formed, column formwork removal is conducted; and S8, earthwork backfilling is conducted. The method has the beneficial effects that only one-time column pouring is needed, special pouring for the foundation bolt is not needed, the pouring construction procedures are reduced, the construction period is shortened, the overall strength of the foundation column is enhanced, and the influence on the tensile property of the foundation bolt is reduced.
本发明公开了一种球型储罐基础柱一次浇筑施工方法,包括以下步骤:S1、在基础柱支墩上安装绑柱筋;S2、在基础柱支墩上安装多根固定型钢;S3、在基础柱支墩周侧安装模具;S4、安装滑移钢板;S5、安装地脚螺栓;S6、进行柱浇筑砼;S7、待柱砼成型再进行柱拆模;S8、进行土方回填。本发明有益效果:只需进行一次性柱浇筑,无需对地脚螺栓进行专门的浇筑,减少了浇筑施工工序和施工周期,增强基础柱整体强度、降低地脚螺栓的抗拉伸性能影响。
One-time pouring construction method for spherical storage tank foundation column
The invention discloses a one-time pouring construction method for a spherical storage tank foundation column. The one-time pouring construction method comprises the following steps that S1, a column binding rib is installed on a foundation column buttress; s2, a plurality of pieces of fixed profile steel are installed on the foundation column buttress; s3, a mold is installed on the peripheral side of the foundation column buttress; s4, a sliding steel plate is installed; s5, foundation bolts are installed; s6, column concrete pouring is conducted; s7, after column concrete is formed, column formwork removal is conducted; and S8, earthwork backfilling is conducted. The method has the beneficial effects that only one-time column pouring is needed, special pouring for the foundation bolt is not needed, the pouring construction procedures are reduced, the construction period is shortened, the overall strength of the foundation column is enhanced, and the influence on the tensile property of the foundation bolt is reduced.
本发明公开了一种球型储罐基础柱一次浇筑施工方法,包括以下步骤:S1、在基础柱支墩上安装绑柱筋;S2、在基础柱支墩上安装多根固定型钢;S3、在基础柱支墩周侧安装模具;S4、安装滑移钢板;S5、安装地脚螺栓;S6、进行柱浇筑砼;S7、待柱砼成型再进行柱拆模;S8、进行土方回填。本发明有益效果:只需进行一次性柱浇筑,无需对地脚螺栓进行专门的浇筑,减少了浇筑施工工序和施工周期,增强基础柱整体强度、降低地脚螺栓的抗拉伸性能影响。
One-time pouring construction method for spherical storage tank foundation column
一种球型储罐基础柱一次浇筑施工方法
LEI MAOJUAN (author) / HU FEI (author) / LI GUANGHUA (author)
2024-12-03
Patent
Electronic Resource
Chinese