A platform for research: civil engineering, architecture and urbanism
MAIN ROPE INSTALLATION METHOD AND OPERATION BAR FOR INSTALLING THE MAIN ROPE
PROBLEM TO BE SOLVED: To ensure safety and reduce costs when installing a main rope on a roof.SOLUTION: A first worker P1 places a first anchor 26 at a first position N1, and places a pilot line 31 and a main rope in a bag for the first anchor 26. The first worker then connects an end of the pilot line 31 to a tip of an operation rod 32, and moves from the first position N1 side to an opposite position on an opposite side of a building 10 while holding the operation rod 32 in such a state. Here, the operation rod 32 is provided with a hook part 33 at the tip, and the pilot line 31 is connected to the tip of the operation rod 32 by hooking its ring part to the hook part 33. The first worker P1 installs the main rope on a roof 13, by removing the pilot line 31 from the operation rod 32 after arriving at the opposite position, and then recovering the pilot line 31 to the opposite position side.
【課題】親綱を屋根に設置する際に安全性を確保し、しかも、コスト負担を低減する。【解決手段】第1作業者P1は、第1位置N1に第1アンカー26を置き、その第1アンカー26について、パイロットライン31及び親綱を袋体に入れておく。そして、操作棒32の先端部にパイロットライン31の一端を接続し、その状態で操作棒32を持って第1位置N1側から建物10の反対側の反対位置に向けて移動する。ここで、操作棒32の先端部には引っ掛け部33が設けられており、パイロットライン31は、そのリング部が引っ掛け部33に引っ掛けられることで操作棒32の先端部に接続されている。第1作業者P1は、反対位置に到着した後、操作棒32からパイロットライン31を取り外し、そのパイロットライン31を反対位置側に回収することで、親綱を屋根13の上に敷設する。【選択図】 図2
MAIN ROPE INSTALLATION METHOD AND OPERATION BAR FOR INSTALLING THE MAIN ROPE
PROBLEM TO BE SOLVED: To ensure safety and reduce costs when installing a main rope on a roof.SOLUTION: A first worker P1 places a first anchor 26 at a first position N1, and places a pilot line 31 and a main rope in a bag for the first anchor 26. The first worker then connects an end of the pilot line 31 to a tip of an operation rod 32, and moves from the first position N1 side to an opposite position on an opposite side of a building 10 while holding the operation rod 32 in such a state. Here, the operation rod 32 is provided with a hook part 33 at the tip, and the pilot line 31 is connected to the tip of the operation rod 32 by hooking its ring part to the hook part 33. The first worker P1 installs the main rope on a roof 13, by removing the pilot line 31 from the operation rod 32 after arriving at the opposite position, and then recovering the pilot line 31 to the opposite position side.
【課題】親綱を屋根に設置する際に安全性を確保し、しかも、コスト負担を低減する。【解決手段】第1作業者P1は、第1位置N1に第1アンカー26を置き、その第1アンカー26について、パイロットライン31及び親綱を袋体に入れておく。そして、操作棒32の先端部にパイロットライン31の一端を接続し、その状態で操作棒32を持って第1位置N1側から建物10の反対側の反対位置に向けて移動する。ここで、操作棒32の先端部には引っ掛け部33が設けられており、パイロットライン31は、そのリング部が引っ掛け部33に引っ掛けられることで操作棒32の先端部に接続されている。第1作業者P1は、反対位置に到着した後、操作棒32からパイロットライン31を取り外し、そのパイロットライン31を反対位置側に回収することで、親綱を屋根13の上に敷設する。【選択図】 図2
MAIN ROPE INSTALLATION METHOD AND OPERATION BAR FOR INSTALLING THE MAIN ROPE
親綱の設置方法及び親綱設置用の操作棒
UETSUKI HIDETAKA (author)
2016-01-18
Patent
Electronic Resource
Japanese
MAIN ROPE HOLDING TOOL AND MAIN ROPE INSTALLATION METHOD
European Patent Office | 2019
|