A platform for research: civil engineering, architecture and urbanism
EMBANKMENT WIDENING METHOD AND EMBANKMENT
To widen an embankment without requiring the construction of steps on an existing embankment.SOLUTION: An embankment widening method is a method for widening an embankment by constructing a widening embankment 3 on an existing embankment 1. This method includes a step of providing a connection layer 2 for the sloping surface of the existing embankment 1, and a step of constructing the widening embankment 3 by piling earth on the connection layer 2. The connection layer 2 has water permeability, and its internal friction angle is larger than that of the existing embankment 1. The N value of the connection layer 2 is larger than those of the existing embankment 1 and the widening embankment 3. The connection layer 2 has a plurality of steps 21 on a surface on the widening embankment 3 side.SELECTED DRAWING: Figure 1
【課題】盛土を拡幅する際に、既設盛土への段切りの施工を不要とする。【解決手段】盛土拡幅工法は、既設盛土1に腹付盛土3を施工して盛土を拡幅する工法である。この工法は、既設盛土1ののり面に接続層2を設ける工程と、接続層2の上に土を盛って腹付盛土3を施工する工程とを有する。接続層2は、透水性を有し、その内部摩擦角が既設盛土1の内部摩擦角より大きく、N値が既設盛土1及び腹付盛土3のN値より大きく、腹付盛土3側の面に複数の段21を有する。【選択図】図1
EMBANKMENT WIDENING METHOD AND EMBANKMENT
To widen an embankment without requiring the construction of steps on an existing embankment.SOLUTION: An embankment widening method is a method for widening an embankment by constructing a widening embankment 3 on an existing embankment 1. This method includes a step of providing a connection layer 2 for the sloping surface of the existing embankment 1, and a step of constructing the widening embankment 3 by piling earth on the connection layer 2. The connection layer 2 has water permeability, and its internal friction angle is larger than that of the existing embankment 1. The N value of the connection layer 2 is larger than those of the existing embankment 1 and the widening embankment 3. The connection layer 2 has a plurality of steps 21 on a surface on the widening embankment 3 side.SELECTED DRAWING: Figure 1
【課題】盛土を拡幅する際に、既設盛土への段切りの施工を不要とする。【解決手段】盛土拡幅工法は、既設盛土1に腹付盛土3を施工して盛土を拡幅する工法である。この工法は、既設盛土1ののり面に接続層2を設ける工程と、接続層2の上に土を盛って腹付盛土3を施工する工程とを有する。接続層2は、透水性を有し、その内部摩擦角が既設盛土1の内部摩擦角より大きく、N値が既設盛土1及び腹付盛土3のN値より大きく、腹付盛土3側の面に複数の段21を有する。【選択図】図1
EMBANKMENT WIDENING METHOD AND EMBANKMENT
盛土拡幅工法及び盛土
FUKADA TAKAHIRO (author) / YAMADA TAKAHIRO (author) / WADA TAKUYA (author) / KOJIMA KENICHI (author)
2019-03-14
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Method of widening embankment foundation at embankment-penetrating building
European Patent Office | 2020
|Embankment widening with the Gap-method