RECONSTRUCTION METHOD OF UNDERGROUND SKELETON
To provide a reconstruction method of an underground skeleton allowing demolition of existing piles without roughening a floor surface upon the demolition of the existing plies.SOLUTION: A reconstruction method of an underground skeleton is to construct a new underground skeleton 2 after demolishing an existing underground skeleton 1 having existing piles 10. The reconstruction method of the underground skeleton includes steps S1 to S3 of arranging a temporary floor surface 34 above a floor surface 35 of the new underground skeleton 2 and excavating the ground from a ground surface 30 to the temporary floor surface 34 while demolishing the existing underground skeleton 1, and a step 4 of demolishing the existing piles 10 to a floor surface level with a heavy machine 36 by deploying the heavy machine 36 on the temporary floor surface 34.SELECTED DRAWING: Figure 6
【課題】既存杭を解体する際、床付面を荒らすことなく既存杭を解体できる、地下躯体の建替え方法を提供すること。【解決手段】地下躯体の建替え方法は、既存杭10を有する既存地下躯体1を解体した後に、新設地下躯体2を構築する。地下躯体の建替え方法は、新設地下躯体2の床付面35より上方に仮床付面34を設定し、地表面30から仮床付面34まで既存地下躯体1を解体しながら掘削するステップS1〜S3と、仮床付面34上に重機36を配置し、重機36で既存杭10を床付面レベルまで解体するステップS4と、を含む。【選択図】図6
RECONSTRUCTION METHOD OF UNDERGROUND SKELETON
To provide a reconstruction method of an underground skeleton allowing demolition of existing piles without roughening a floor surface upon the demolition of the existing plies.SOLUTION: A reconstruction method of an underground skeleton is to construct a new underground skeleton 2 after demolishing an existing underground skeleton 1 having existing piles 10. The reconstruction method of the underground skeleton includes steps S1 to S3 of arranging a temporary floor surface 34 above a floor surface 35 of the new underground skeleton 2 and excavating the ground from a ground surface 30 to the temporary floor surface 34 while demolishing the existing underground skeleton 1, and a step 4 of demolishing the existing piles 10 to a floor surface level with a heavy machine 36 by deploying the heavy machine 36 on the temporary floor surface 34.SELECTED DRAWING: Figure 6
【課題】既存杭を解体する際、床付面を荒らすことなく既存杭を解体できる、地下躯体の建替え方法を提供すること。【解決手段】地下躯体の建替え方法は、既存杭10を有する既存地下躯体1を解体した後に、新設地下躯体2を構築する。地下躯体の建替え方法は、新設地下躯体2の床付面35より上方に仮床付面34を設定し、地表面30から仮床付面34まで既存地下躯体1を解体しながら掘削するステップS1〜S3と、仮床付面34上に重機36を配置し、重機36で既存杭10を床付面レベルまで解体するステップS4と、を含む。【選択図】図6
RECONSTRUCTION METHOD OF UNDERGROUND SKELETON
地下躯体の建替え方法
MATSUI TSUYOSHI (author) / SAKOTA KEISUKE (author)
2021-06-24
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,